January 2015 Workbook
Implemented Modifications to the 2015 Standard Specifications
January 2015 Workbook
for Lettings Effective January - June 2015
Special Provisions - Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.
Supplemental Specifications - Additions or revisions to the Standard Specifications.
History of Revisions - To review the History of revisions for this Workbook.
Mandatory Revisions - Critical modifications implemented for the Workbook.
Mandatory Revision #3 - To review the implementation letter.
Mandatory Revision #2 - To review the implementation letter.
Mandatory Revision #1 - To review the implementation letter.
Workbook Document - Final - To review the changes to the Workbook.
Workbook Document - Draft - To review the Workbook.
Note: These files are in Adobe Acrobat (PDF) format.
File size ranges from 9 kb to 200 kb.
SPECIAL PROVISIONS | SP0000001 | Usage Note |
---|---|---|
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF WORK. (REV 2-19-14) (FA 2-20-14) (1-15) Insert Information Required. Change(s) to: 2-4. | SP0020400 | All Jobs, (add a phone number or e-mail address) |
PREPARATION OF PROPOSALS. (REV 6-22-04) (FA 7-13-04) (1-15) Change(s) to: 2-5.1. | SP0020501AB | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0030100AB, SP0030203AB,SP0080701AB and SP0081300AB |
PREPARATION OF PROPOSALS. (REV 2-21-05) (FA 3-31-05) (1-15) Insert Information Required. Change(s) to: 2-5.1. | SP0020501LR | Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0030100LR, SP0081300LRDR and SP0081300LR |
CONSIDERATION OF BIDS - SCOPE ALTERNATES. (REV 4-23-13) (FA 5-14-13) (1-15) Change(s) to: 3-1. | SP0030100 | Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions. Notify Contracts Office on Transmittal Memo. |
AWARD AND EXECUTION OF CONTRACT. (REV 11-5-97) (FA 1-20-98) (1-15) Insert Information Required Change(s) to: 3-1. | SP0030100AB | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030203AB, SP0080701AB and SP0081300AB |
BUDGETARY CONSTRAINTS. (REV 9-26-06) (FA 10-6-06) (1-15) Insert Information Required Change(s) to: 3-1. | SP0030100BC | Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions. Notify the Contracts Administration Office on the Transmittal Memo. |
AWARD AND EXECUTION OF CONTRACT. (REV 12-21-12) (1-10-13) (1-15) Change(s) to: 3-1, 3-2.2, 3-5.1. | SP0030100DC | District Let Construction Contracts less than $250,000 and all Maintenance Contracts, excluding Lump Sum |
AWARD AND EXECUTION OF CONTRACT. (REV 4-11-97) (FA 5-7-97) (1-15) Change(s) to: 3-1. | SP0030100LR | Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0081300LR and SP0081300LRDR |
AWARD AND EXECUTION OF CONTRACT. (REV 8-1-00) (1-15) Change(s) to: 3-1. | SP0030100LS | Lump Sum Projects |
AWARD AND EXECUTION OF CONTRACT. (REV 7-26-01) (1-15) Insert Information Required Change(s) to: 3-2, 3-6, 3-7. | SP0030200 | When necessary to change standard “Award and Execution” Contracts Office must approve. |
AWARD OF CONTRACTS - A+B BIDDING (REV 8-22-96) (FA 9-3-96) (1-15) Insert Information Required Change(s) to: 3-2. | SP0030203AB | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB,SP0080701AB and SP0081300AB |
SCOPE OF THE WORK - INTENT OF CONTRACT. (REV 8-19-09) (FA 8-24-09) (1-15) Insert Information Required. Change(s) to: 4-1. | SP0040100 | All Jobs, excluding Lump Sum. Do not use with SP0040100SLPQ. |
SCOPE OF THE WORK. (REV 8-24-10) (FA 10-8-10) (1-15) Insert Information Required. Change(s) to: 4-1, 4-3.1, 4-3.4, 4-3.9.4. | SP0040100LS | All Lump Sum Projects. Do not use with SP0040100SLLS. |
SCOPE OF THE WORK - INTENT AND SCOPE. (REV 8-24-10) FA 10-8-10) (1-15) Insert Information Required. Change(s) to: 4-14-3.1, 4-3.4, 4-3.9.4. | SP0040100SLLS | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Lump Sum. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0040100LS. |
SCOPE OF THE WORK - INTENT AND SCOPE. (REV 9-16-09) (FA 11-9-09) (1-15) Insert Information Required. Change(s) to: 4-1, 4-3.1, 4-3.4, 4-3.9.4. | SP0040100SLPQ | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Plan Quantity. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0040100. |
UNFORESEEABLE WORK. (REV 9-28-98) (1-15) Change(s) to: 4-4. | SP0040400 | 999-25 |
CONTROL OF THE WORK. (REV 3-15-02) (1-15) Change(s) to: 5-1.1, 5-2, 5-7.6. | SP0050101LS | Lump Sum Projects |
INSPECTION. (REV 2-10-94) (1-15) Change(s) to: 5-9.1 | SP0050901 | Long bridge jobs (1500 feet or longer); modify to suit |
CONTROL OF MATERIALS. (REV 8-17-09) (FA 8-24-09) (1-15) Change(s) to: 6-1. | SP0060100LS | Lump Sum Projects |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - COMPLIANCE WITH FHWA 1273. (REV 1-2-14) (1-16-14) (1-15) Change(s) to: 7-1.1. | SP0070101 | All Federal Aid Jobs |
PERMITS PROCURED BY THE DEPARTMENT. (REV 8-7-01) (FA 4-14-05) (1-15) Change(s) to: 7-2.1. | SP0070201A | Jobs with permit(s) procured by DOT |
DISCHARGE TO OR WORK OR STRUCTURES IN NAVIGABLE WATERS OF THE U.S., WATERS OF THE U.S. AND WATERS OF THE STATE. (REV 7-16-09) (FA 7-30-09) (1-15) Change(s) to: 7-2.2. | SP0070202 | When SWPPP is used. (One or more acres disturbed.) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC. (REV 4-18-14) (1-15) Change(s) to: 7-7.1, 7-13.2, 7-13.3. | SP0070701DC | District Let Contracts less than $250,000 and all Maintenance Contracts. |
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - OPERATIONS WITHIN RAILROAD RIGHT-OF-WAY. (REV 11-5-10) (FA 11-9-10) (1-15) Change(s) to: 7-11.5. | SP0071104 | Projects Involving CSX Transportation. |
UTILITY WORK. (REV 2-10-94) (1-15) Change(s) to: 7-11.5.3. | SP0071153A | When there are no utility work schedules |
UTILITY SCHEDULES. (REV 8-27-01) (FA 4-14-05) (1-15) Change(s) to: 7-11.5.3. | SP0071153B | When there are utility work schedules |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WAGE RATES FOR FEDERAL-AID PROJECTS. (REV 12-21-09) (FA 12-28-09) (1-15) Insert Information Required. Change(s) to: 7-16. | SP0071600 | All Federal Aid Jobs |
EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS. (REV 4-25-02) (FA 7-17-02) (1-15) Change(s) to: Section 7-26. | SP0072600 | Non-Federal Aid Projects |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PREFERENCE TO STATE RESIDENTS. (REV 1-13-12) (1-15) Change(s) to: Section 7. | SP0072700 | Non-Federal Aid Projects - Construction Projects Only |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - E-VERIFY. (REV 6-13-11) (FA 6-16-11) (1-15) Change(s) to: Section 7. | SP0072800 | All Jobs |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - SCRUTINIZED COMPANIES. (REV 6-17-11) (1-15) Change(s) to: Section 7. | SP0072900 | All Jobs |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - TITLE VI ASSURANCE - DOT 1050.2, APPENDIX A. (REV 11-12-13) (FA 11-26-13) (1-15) Change(s) to: Section 7. | SP0073000 | All Federally Funded Jobs. |
PROSECUTION AND PROGRESS - SUBMISSION OF WORKING SCHEDULE. (REV 1-11-11) (FA 5-12-11) (1-15) Change(s) to: 8-3.2. | SP0080302A | Use only when CPM is authorized by District Construction Engineer. Do not use with SP0080302DC. |
PROSECUTION AND PROGRESS. (REV 6-18-12) (1-15) Change(s) to: 8-3.2, 8-8, 8-9.1. | SP0080302DC | District Let Contracts (including Lump Sum) less than $250,000, and all Maintenance Contracts. Do not use with SP0080302A. |
PROSECUTION OF WORK - FLEXIBLE START TIME. (REV 2-15-10) (FA 2-17-10) (1-15) Insert Information Required Change(s) to: 8-3.3. | SP0080303A | When called for by the District Construction Engineer or the District Maintenance Engineer/Administrator. *Contracts Office must be notified. |
BEGINNING WORK. (REV 7-10-95) (7-14) Insert Information Required Change(s) to: 8-3.3. | SP0080303B | When called for by the District Construction Engineer. Use with the approval of the Chief Engineer. |
BEGINNING WORK. (REV 10-22-98) (11-5-98) (1-15) Insert Information Required. Change(s) to: 8-3.3. | SP0080303C | When called for by the District Construction Engineer. Use with the approval of the Chief Engineer. *Contracts Office must be notified. |
PROSECUTION OF WORK - PARTNERING. (REV 5-5-12) (FA 5-21-12) (1-15) Insert Information Required. Change(s) to: 8-3.3. | SP0080306 | 999-16* *Contracts Office must be notified |
PROSECUTION OF WORK - DISPUTES REVIEW BOARD. (REV 1-4-11) (FA 1-21-11) (1-15) Change(s) to: 8-3. | SP0080307DRB | 999-20 Items Contracts Office must be notified |
PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD. (REV 1-4-11) (FA 1-21-11) (1-15) Change(s) to: 8-3. | SP0080307RDRB | Jobs without 999-20 Items |
PROSECUTION OF WORK - STATEWIDE DISPUTES REVIEW BOARD. (REV 1-4-11) (FA 1-21-11) (1-15) Change(s) to: 8-3. | SP0080308SDRB | 334, 337, 350, 570, 580 or 649 Items. |
PROSECUTION AND PROGRESS. (REV 8-1-00) (1-15) Change(s) to: 8-4.1, 8-7.3.1. | SP0080401LS | Lump Sum Projects |
LIMITATIONS OF OPERATIONS - FENCING. (REV 6-17-04) (FA 7-13-04) (1-15) Change(s) to: 8-4.8. | SP0080408 | Jobs on Limited Access Highways |
CONTAMINATED MATERIAL - MERCURY-CONTAINING DEVICES AND LAMPS. (REV 11-6-95) (FA 12-27-95) (1-15) Insert Information Required. Change(s) to: 8-4.9. | SP0080409 | Jobs with Lighting* |
COMPUTATION OF CONTRACT TIME. (REV 12-22-98) (FA 1-19-99) (1-15) Insert Information Required. Change(s) to: 8-7.1. | SP0080701A | Use with approval of the District Construction Engineer. |
COMPUTATION OF CONTRACT TIME. (REV 7-24-96) (FA 9-3-96) (1-15) Change(s) to: 8-7.1. | SP0080701AB | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB,SP0030203AB and SP0081300AB |
COMPUTATION OF CONTRACT TIME. (REV 2-14-94) (1-15) Insert Information Required. Change(s) to: 8-7.1. | SP0080701B | Use with the approval of the District Construction Engineer. |
COMPUTATION OF CONTRACT TIME. (REV 12-22-98) (FA 2-1-99) (1-15) Change(s) to: 8-7.1. | SP0080701C | Use when requested by the District Construction Engineer. |
DAMAGE RECOVERY. (REV 2-4-04) (1-15) Insert Information Required. Change(s) to: Section 8. | SP0081300 | Use when requested by the District Construction Engineer. (Do not use with Lane Rental) |
PROSECUTION AND PROGRESS. (REV 7-28-97) (1-15) Change(s) to: Section 8. | SP0081300A | All Jobs with Alternative Bidding. Use with the approval of the District Construction Engineer. |
8-13. Incentive - Disincentive for A+B. (REV 7-27-04) (FA 7-28-04) (1-13) Insert Information Required. Change(s) to: 8-13. | SP0081300AB | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB, SP0030203AB and SP0080701AB |
8-13. "Bonus" Payment and Waiver of Contractor Claims. (REV 5-19-04) (FA 7-13-04) (1-05) Insert Information Required. Change(s) to: 8-13. | SP0081300ABB | A+B Jobs with Bonus Use with the approval of the District Construction Engineer. |
8-13. " Bonus " Payment and Waiver of Contractor Claims. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. | SP0081300B | Bonus (Date Specific) Use with the approval of the District Construction Engineer. |
8-13. "Bonus" Payment and Waiver of Contractor Claims. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. | SP0081300BCD | Bonus (Calendar Days) Use with the approval of the District Construction Engineer. |
8-13. Incentive - Disincentive. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. | SP0081300ID | Incentive - Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300MID. |
8-13. Incentive - Disincentive for Lane Rental Days. (REV 9-25-03) (FA 12-24-03) (7-04) Insert Information Required. Change(s) to: 8-13. | SP0081300IDLR | Incentive-Disincentive for Lane Rental Days. Use with the approval of the District Construction Engineer. Do not use with SP0081300LR or SP0081300LRDR |
8-13. Liquidated Savings for Early Completion. (REV 5-18-99) (FA 6-10-99) (7-00) Insert Information Required. Change(s) to: 8-13. | SP0081300LQS | Liquidated Savings. Use with the approval of the District Construction Engineer. |
8-13. Pay Adjustment For Fewer-More Lane Rental Days. (REV 4-29-97) (FA 5-7-97) (7-00) Change(s) to: 8-13. | SP0081300LR | Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR and SP0081300LRDR. |
8-13. Damage Recovery. (REV 9-25-03) (FA 12-24-03) (7-04) Insert Information Required. Change(s) to: 8-13. | SP0081300LRDR | Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR and SP0081300LR. |
8-13. "Bonus" Payment and Waiver of Contractor Claims. (REV 4-12-06) (FA 4-25-06) (1-07) Insert Information Required. Change(s) to: 8-13. | SP0081300MB | Milestone Bonus Use with the approval of the District Construction Engineer. Do not use with SP0081300B or SP0081300BCD |
8-13. Incentive - Disincentive. (REV 2-9-06) (FA 4-25-06) (1-07) Insert Information Required. Change(s) to: 8-13. | SP0081300MID | Milestone Incentive-Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300ID |
MEASUREMENT AND PAYMENT. (REV 4-9-14) (FA 4-29-14) (1-15) Change(s) to: 9-1.3, 9-2, 9-3, 9-5.5.2, 9-9, 9-11. | SP0090103LS | Lump Sum Projects. Do not use with SP0090103SLLS. |
MEASUREMENT AND PAYMENT. (REV 2-25-14) (FA 5-6-14) (1-15) Change(s) to: 9-1.3, 9-2, 9-3, 9-5.1, 9-8.1, 9-9. | SP0090103SLLS | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Lump Sum. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0090103LS. |
MEASUREMENT AND PAYMENT. (REV 2-25-14) (FA 5-6-14) (1-15) Change(s) to: 9-1.3.2, 9-2, 9-3.2.3, 9-5.1, 9-8.1, 9-9, 9-11. | SP0090103SLPQ | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline Plan Quantity. For Bridge repair/rehab projects, contact the DCE prior to use. Do not use with SP0090501DC. |
MEASUREMENT AND PAYMENT. (REV 10-29-08) (FA 1-16-09) (1-15) Change(s) to: 9-5.1, 9-5.4, 9-9. | SP0090501DC | District Let Contracts. Excluding Lump Sum Projects. Do not use with SP0090103SLPQ. |
ENGINEER'S FIELD OFFICE. (REV 5-8-13) (FA 5-16-13) (1-15) Change(s) to: 109. | SP1090000 | 109-71 Items |
REMOVAL OF EXISTING STRUCTURES - STRUCTURES TO BE REMOVED. (REV 9-10-07) (FA 2-15-08) (1-15) Insert Information Required. Change(s) to: 110-6.1. | SP1100601 | Use with approval of the District Construction Engineer and signed Agreement from the Local Agency receiving the material. |
REMOVAL OF EXISTING STRUCTURES. (REV 1-29-13) (FA 2-15-13) (1-15) Change(s) to: 110-6.6. | SP1100606 | Use when areas of Asbestos Abatement are identified in the Plans |
MATERIAL FOR REEF ESTABLISHMENT. (REV 7-10-95) (FA 6-21-99) (1-15) Change(s) to: 110-11.2, 110-12.7. | SP1101102 | 110-84 |
EXCAVATION - INDENTIFIED AREAS OF CONTAMINATION. (REV 1-29-13) (FA 2-15-13) (1-15) Change(s) to: 120-1. | SP1200100A | Use when contaminated areas are delineated in the plans |
EXCAVATION AND EMBANKMENT - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (1-15) Change(s) to: 120-10.3.1. | SP1201003SL | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use. |
EXCAVATION FOR STRUCTURES AND PIPE - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (1-15) Change(s) to: 125-9.3.1. | SP1250903SL | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use. |
STABILIZING - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (1-15) Change(s) to: 160-4.2.4. | SP1600402SL | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use. |
ROCK BASE - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (1-15) Change(s) to: 200-7.2.2 | SP2000702SL | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use. |
GRADED AGGREGATE BASE. (REV 8-8-07) (1-15) Change(s) to: 204. | SP2040000 | 285 Items. Do not use on Interstate Projects. |
MILLING OF EXISTING ASPHALT PAVEMENT. (REV 8-31-99) (FA 2-14-00) (1-15) Insert Information Required. Change(s) to: 327-1, 327-6. | SP3270100 | When the plans provide a location for stockpiling milled material. Insert quantity to be retained. Use "all, tons, square yards", etc. |
MILLING OF EXISTING ASPHALT PAVEMENT. (REV 12-1-93) (1-15) Change(s) to: 327-2. | SP3270200 | Use when requested by districts |
PORTLAND CEMENT CONCRETE - ACCEPTANCE SAMPLING FREQUENCY. (REV 6-25-10) (FA 7-8-10) (1-15) Change(s) to: 346-9.2. | SP3460902SL | All Contracts less than $2,000,000 and less than 2,000 tons of asphalt - Streamline. For Bridge repair/rehab projects, contact the DCE prior to use. |
INTEGRAL PILE JACKETS. (REV 11-16-11) (FA 12-8-11) (1-15) Change(s) to: 457. | SP4570000 | 457 Items |
LANDSCAPING. (REV 3-15-13) (1-15) Change(s) to: 580. | SP5800000 | Non-Federal Aid Jobs with Landscaping. Use when requested by the DDE. |
LANDSCAPING. (REV 3-15-13) (1-15) Change(s) to: 580. | SP5800000FA | All Federal Aid Jobs with Landscaping. Use when requested by the DDE. |
GALVANIZED STEEL POLES, MAST ARMS AND MONOTUBE ASSEMBLIES. (REV 10-13-14) (1-15) Change(s) to: 649. | SP6490000 | All Jobs Mandatory No. 2 |
VEHICULAR TRAFFIC SIGNAL ASSEMBLIES. (REV 10-10-14) (1-15) Change(s) to: 650. | SP6500000 | All Jobs Mandatory No. 2 |
MAST ARM, SPAN WIRE, AND POLE MOUNTING ASSEMBLIES. (REV 10-10-14) (1-15) Change(s) to: 659. | SP6590000 | All Jobs Mandatory No. 2 |
TRAFFIC CONTROL SYSTEM AUXILIARIES. (REV 11-5-14) (1-15) Change(s) to: 685. | SP6850000 | 685 Items Mandatory No. 3 |
TRAFFIC MONITORING SITE VEHICLE SENSOR - NON-WEIGHT APPLICATIONS. (REV 1-3-12) (FA 1-27-12) (1-15) Change(s) to: 741. | SP7410000 | 741-1 Items |
TRAFFIC MONITORING SITE VEHICLE SPEED/CLASSIFICATION UNIT. (REV 6-16-99) (FA 7-20-99) (1-15) Change(s) to: 743. | SP7430000 | 743-70 Items |
TRAFFIC MONITORING SITE SOLAR POWER UNIT. (REV 10-22-10) (FA 11-22-10) (1-15) Change(s) to: 744. | SP7440000 | 744-70 Items |
TRAFFIC MONITORING SITE INDUCTIVE LOOP ASSEMBLY. (REV 1-10-13) (FA 1-15-13) (1-15) Change(s) to: 745. | SP7450000 | 745-70 Items |
TRAFFIC MONITORING SITE CABINET. (REV 5-6-08) (FA 10-14-08) (1-15) Change(s) to: 746. | SP7460000 | 746-7A-BCD |
TRAFFIC MONITORING SITE MODEM. (REV 5-20-99) (FA 7-20-99) (1-15) Change(s) to: 747. | SP7470000 | 747-70 Items |
GENERAL REQUIREMENTS FOR THE EVALUATION OF TRAFFIC MONITORING SITE EQUIPMENT AND MATERIALS. (REV 5-12-99) (FA 7-20-99) (1-15) Change(s) to: 748. | SP7480000 | Jobs with Traffic Monitoring Sites |
Supplemental Specifications | SS0000001 | Usage Note |
102 MAINTENANCE OF TRAFFIC. (REV 10-28-14) (FA 11-6-14) (1-15) Change(s) to: 102-3.2, 102-6.2, 102-9.1, 102-9.2, 102-9.5, 102-11.3, 102-11.5, 102-11.8, 102-11.22, 102-11.23. | SS1020302 | All Jobs Mandatory No. 1 and Mandatory No. 3 |
471 FIBER REINFORCED POLYMER FENDER SYSTEMS. (REV 8-15-14) (FA 9-10-14) (1-15) Change(s) to: 471. | SS4710000 | All Jobs Mandatory No. 1 |
653 PEDESTRIAN SIGNAL ASSEMBLIES. (REV 9-4-14) (FA 9-16-14) (1-15) Change(s) to: 653. | SS6530000 | All Jobs Mandatory No. 1 |
670 TRAFFIC CONTROLLER ASSEMBLIES. (REV 7-29-14) (FA 9-10-14) (1-15) Change(s) to: 670. | SS6700000 | All Jobs Mandatory No. 1 |
676 TRAFFIC CABINETS. (REV 9-5-14) (FA 9-10-14) (1-15) Change(s) to: 676. | SS6760000 | All Jobs Mandatory No. 1 |
985 GEOSYNTHETIC MATERIALS. (REV 9-2-14) (FA 9-10-14) (1-15) Change(s) to: 985. | SS9850000 | All Jobs Mandatory No. 1 |
Appendices | XAPENCIC | Jobs with TSPs |
TECHNICAL SPECIAL PROVISIONS.
The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package.
| XTSPs | Jobs with TSPs |