Error processing SSI file
Structures
Design Office
- Fuller Warren Bridge
 |
Location:
Jacksonville, FL
Owner: Florida Department of Transportation
Designer: HNTB Corporation
Inspectors: Parsons Brinckerhoff Const. Services |
Physical Description:
The replacement structure
consists of 52 spans totaling more than 7,500 feet and conveying eight lanes of traffic,
four in each direction. The main span over the shipping channel is 250 feet with a
vertical clearance of 75 feet.
Project
Description:
In July 1990, FDOT District Two retained HNTB to assist the Department in Project
Development and Environmental Study for the Fuller Warren Bridge replacement. In 1992,
HNTB was retained for Final Design. The existing Fuller Warren Bascule Bridge is one of
two moveable bridges located on the Interstate. The project includes 1.4 miles of mainline
bridge, 3000 feet of ramp on structure, 77,000 sq. ft. of MSE and cast-in-place retaining
wall, drainage and roadway improvements, lighting, signing and traffic control. The
existing Fuller Warren bridge is a four lane structure with no emergency lanes. The
superstructure is concrete slab on steel rolled shapes or steel underslung trusses. The
channel span is a double leaf bascule spanning about 175 ft. The bridge carries 100,000
vehicles a day on I-95, over the St. Johns River in Jacksonville. It was opened in 1954.
The existing bridge is being replaced for several reasons including its substandard
roadway width, frequently needed repairs and its being one of two stop conditions
remaining on this major north - south expressway. To counteract the need for costly
repairs before the new bridge is in service, the existing bridge is currently closed to
vehicles with more than two axles.
The new bridge will provide three lanes in each direction for I-95 and an auxiliary lane
in each direction for traffic to enter or exit I-95. Four 10 foot shoulders are provided.
The main span is 250 feet and provides 75 feet of vertical clearance. The new bridge
superstructures type is slab and PPC I-beam. Approach spans with few exceptions are 140
feet in length and use 78" Modified Bulb Tee beams made continuous for live load. At
the east end of the project an existing bridge over the FEC railroad constructed with
steel beams and Type II AASHTO girders is being widened in kind. At the west end of the
project four spans of Type V AASHTO girders are detailed. Elastomeric bearing pads are
used throughout the project except at the three span channel unit where pot bearings will
be installed. Seismic continuity between the super and sub-structure is provided by 1
½" diameter dowels cast into and projecting out of the top of the pier caps. The
projecting dowels then reside inside 8" X 4" structural tube sections cast into
the bottom surface of end diaphragms. The superstructure is supported by hammerhead type
piers founded on 36", 48" or 72" diameter drilled shafts. The land pier
columns are cast-in-place. The river pier columns and all of the beams on the project are
precast at a yard set up and operated by BBCI for this project in Greencove Springs
located about 30 miles south of the project on the St. Johns River. Precast elements are
delivered down river to the construction site by barge.
Dates:
PD&E Study: 1990
Final Design Contract: 1992
Estimated Completion: March 2002
Cost:
Owner's Est. $112 Million, Project Bid $81 Million
Unique
Features:
The 650 channel unit is 3 continuous
spans (200-250-200) made of 3 - 80" deep modified bulb tee segments
and 2 haunched pier segments. The haunched pier segments transition from 120" deep at
the piers to 80" deep at the ends. Each 5 segment run is post-tensioned by three
tendons made of 15 - 0.6" prestressing strands running the length of the unit through
the 8" beam webs.The erection method used for the channel unit calls for a temporary
support system utilizing temporary piers to support the haunched pier segments and
"strongbacks" to support the end segments and center segments (drop-in-beams).
The project is architecturally enhanced by understating pier cap strength with
post-tensioning, using buttresses and copings at pier cap to column connections, shaping
pier columns using octagonal shapes and rustication and finally by coating all viewable
concrete surfaces with a Class V Finish Coating.
|