Specifications and Estimates
Implemented Modifications to the 2010 Standard Specifications
July 2010 Workbook
for Lettings Effective July - December 2010
Special Provisions - Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.
Supplemental Specifications - Additions or revisions to the Standard Specifications.
Change Table - Shows all changes made to the Specifications within this workbook.
Change Table - Updated 5-18-10 - Shows all changes made to the Specifications within this workbook.
Change Table - Updated 6-30-10 - Shows all changes made to the Specifications within this workbook.
History of Revisions - To review the History of revisions for this Workbook.
Mandatory Revisions - Critical modifications implemented for the Workbook.
Mandatory Revision #2 - To review the implementation letter.
Mandatory Revision #1 - To review the implementation letter.
Workbook Document - Redline - To review the changes to the Workbook.
Workbook Document - Final - To review the Workbook.
Workbook Document - Updated 5-18-10 - To review the Workbook.
Workbook Document - Updated 6-30-10 - To review the Workbook.
Note: These files are in Adobe Acrobat (PDF) format. File size ranges from 9 kb to 279 kb.
| SPECIAL PROVISIONS | SP0000001 | All Jobs | |
|---|---|---|---|
|
Mandatory Revision No.2 (REV 2-7-08) (FA 2-13-08) (7-08) Insert Information Required. Change(s) to: 2-4. |
SP0020400 |
||
|
Mandatory Revision No.2 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF WORK. (REV 4-28-10) (FA 5-17-10) (12-10) Insert Information Required. Change(s) to: 2-4. |
SP0020400 | All Jobs, (add a phone number or e-mail address) | |
|
PREPARATION OF PROPOSALS. (REV 6-22-04) (FA 7-13-04) (1-05) Change(s) to: 2-5.1. |
SP0020501AB | A+B Bidding. (Use with proper authority). Use with SP0030100AB, SP0030203,SP0081300AB and SP0080701AB | |
|
PREPARATION OF PROPOSALS. (REV 2-21-05) (FA 3-31-05) (1-06) Insert Information Required. Change(s) to: 2-5.1. |
SP0020501LR | Lane Rental. (Use with proper authority). Use with SP0030100LR, SP0081300LR and SP0081300LRDR | |
|
CONSIDERATION OF BIDS - SCOPE ALTERNATES. (REV 2-15-07) (1-10) Change(s) to: 3-1. |
SP0030001 | (Use with proper authority.) *Notify Contracts Office on Transmittal Memo. | |
|
AWARD AND EXECUTION OF CONTRACT. (REV 11-5-97) (FA 1-20-98) (7-00) Insert Information Required Change(s) to: 3-1. |
SP0030100AB | A+B Bidding. (Use with proper authority). Use with SP0020501AB, SP0030203,SP0080701AB and SP0081300AB | |
|
BUDGETARY CONSTRAINTS. (REV 9-26-06) (FA 10-6-06) (1-07) Insert Information Required Change(s) to: 3-1. |
SP0030100BC | Use on Projects over $25 M. Notify the Contracts Administration Office on the Transmittal Memo. | |
|
AWARD AND EXECUTION OF CONTRACT. (REV 6-22-07) (7-07) Insert Information Required Change(s) to: 3-1. |
SP0030100DC | All District Let and Maintenance Contracts excluding Lump Sum | |
|
AWARD AND EXECUTION OF CONTRACT. (REV 4-11-97) (FA 5-7-97) (7-00) Change(s) to: 3-1. |
SP0030100LR | Lane Rental. (Use with proper authority). Use with SP0020501LR, SP0081300LR and SP0081300LRDR | |
|
AWARD AND EXECUTION OF CONTRACT. (REV 8-1-00) (1-01) Change(s) to: 3-1. |
SP0030100LS | Lump Sum Projects | |
|
AWARD AND EXECUTION OF CONTRACT. (REV 7-26-01) (7-10) Insert Information Required Change(s) to: 3-2, 3-6, 3-7. |
SP0030200 | When necessary to change standard “Award and Execution”* *Contracts Office must approve |
|
|
AWARD AND EXECUTION OF CONTRACT. (REV 2-7-97) (1-10) Change(s) to: 3-2.1, 3-2.2, 3-4, 3-7 |
SP0030201 | Bid Average Method (Use with proper authority) | |
|
AWARD OF CONTRACTS - A+b BIDDING (REV 8-22-96) (FA 9-3-96) (1-10) Insert Information Required Change(s) to: 3-2. |
SP0030203 | A+B Bidding. (Use with proper authority). Use with SP0020501AB, SP0030100AB,SP0080701AB and SP0081300AB | |
|
SCOPE OF THE WORK - INTENT AND SCOPE. (REV 8-19-09) (FA 8-24-09) (1-10) Insert Information Required. Change(s) to: 4-1. |
SP0040100 | All Jobs, except Lump Sum | |
|
SCOPE OF THE WORK. (REV 2-15-10) (FA 2-17-10) (7-10) Insert Information Required. Change(s) to: 4-1, 4-3.1, 4-3.4, 4-3.9.4. |
SP0040100LS | All Lump Sum Projects. Do not use with SP0040100SLLS. | |
|
SCOPE OF THE WORK - INTENT AND SCOPE. (REV 2-15-10) (FA 2-17-10) (7-10) Insert Information Required. Change(s) to: 4-1. |
SP0040100SLLS | Streamline Lump Sum Projects less than $2,000,000 and less than 2,000 tons of asphalt. Do not use with SP0040100LS. | |
|
SCOPE OF THE WORK - INTENT AND SCOPE. (REV 9-16-09) (FA 11-9-09) (7-10) Insert Information Required. Change(s) to: 4-1, 4-3.1, 4-3.4, 4-3.9.4. |
SP0040100SLPQ | Streamline Plan Quantity Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
SCOPE OF THE WORK. (REV 7-20-06) (1-07) Change(s) to: 4-1. |
SP0040100M | All Metric Jobs | |
|
VALUE ENGINEERING INCENTIVE. (REV 8-12-96) (FA 7-2-97) (1-10) Change(s) to: 4-3.9. |
SP0040309DC | District Let Contracts less than $250,000 and all Maintenance Contracts. Excluding Lump Sum | |
|
UNFORESEEABLE WORK. (REV 9-28-98) (1-10) Change(s) to: 4-4. |
SP0040400 | 999-25 | |
|
CONTROL OF THE WORK. (REV 3-15-02) (1-10) Change(s) to: 5-1.1, 5-2, 5-7.6. |
SP0050501LS | Lump Sum Projects | |
|
INSPECTION. (REV 2-10-94) (1-10) Insert Information Required. Change(s) to: 5-9.1 |
SP0050901 | Long bridge jobs (1500 feet or longer); modify to suit | |
|
CONTROL OF MATERIALS. (REV 8-17-09) (FA 8-24-09) (1-10) Change(s) to: 6-1. |
SP0060100LS | Lump Sum Projects | |
|
REQUIREMENTS FOR FEDERAL JOBS - COMPLIANCE WITH FHWA 1273. (REV 2-11-10) (FA 2-17-10) (7-10) Change(s) to: 7-1.1. |
SP0070101 | All Federal Aid Jobs | |
|
LAWS TO BE OBSERVED. (REV 3-31-09) (FA 6-17-09) (1-10) Change(s) to: 7-1.1.1. |
SP0070111ES | All American Recovery and Reinvestment Act of 2009 Jobs | |
|
PERMITS PROCURED BY THE DEPARTMENT. (REV 8-7-01) (FA 4-14-05) (1-10) Change(s) to: 7-2.1. |
SP0070201A | Jobs with permit(s) procured by DOT | |
|
DISCHARGE TO OR WORK OR STRUCTURES IN NAVIGABLE WATERS OF THE U.S.,
WATERS OF THE U.S. AND WATERS OF THE STATE. (REV 7-16-09) (FA 7-30-09) (1-10) Change(s) to: 7-2.2. |
SP0070202 | When DEP Generic Permit is required | |
|
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC. (REV 1-9-01) (1-10) Insert Information Required. Change(s) to: 7-7.1, 7-13.2, 7-13.3. |
SP0070701DC | District Let Contracts less than $250,000 and all Maintenance Contracts. | |
|
USE OF EXPLOSIVES. (REV 9-26-94) (1-10) Change(s) to: 7-9. |
SP0070900 | When explosives are prohibited | |
|
UTILITY WORK. (REV 2-10-94) (1-10) Change(s) to: 7-11.6.3. |
SP0071163A | When there are no utility work schedules | |
|
UTILITY SCHEDULES. (REV 8-27-01) (FA 4-14-05) (1-10) Change(s) to: 7-11.6.3. |
SP0071163B | When there are utility work schedules | |
|
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WAGE RATES FOR FEDERAL-AID PROJECTS.
(REV 12-21-09) (FA 12-28-09) (7-10) Insert Information Required. Change(s) to: 7-16. |
SP0071600 | All Federal Aid Jobs | |
|
EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS. (REV 4-25-02) (FA 7-17-02) (1-10) Change(s) to: Section 7-26. |
SP0072600 | Non-Federal Aid Projects | |
|
Mandatory Revision No.2 LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PREFERENCE TO STATE RESIDENTS. (REV 6-15-10) (9-10) Change(s) to: Section 7. |
SP0072700 | Non-Federal Aid Projects - Construction Projects Only | |
|
SUBMISSION OF WORKING SCHEDULE. (REV 6-3-09) (FA 6-10-09) (1-10) Change(s) to: 8-3.2. |
SP0080302A | Use only when CPM is authorized by District Construction Engineer. Do not use with SP0080302DC. | |
|
PROSECUTION AND PROGRESS. (REV 2-27-01) (1-10) Change(s) to: 8-3.2, 8-8, 8-9.1. |
SP0080302DC | District Let Contracts (including Lump Sum) less than $250,000, and all Maintenance Contracts. Do not use with SP0080302A. | |
|
PROSECUTION OF WORK - FLEXIBLE START TIME. (REV 2-15-10) (FA 2-17-10) (7-10) Insert Information Required Change(s) to: 8-3.3. |
SP0080303A | When called for* *Contracts Office must be notified. |
|
|
BEGINNING WORK.
(REV 7-10-95) (1-10) Insert Information Required Change(s) to: 8-3.3. |
SP0080303B | When called for by the District Construction Engineer | |
|
BEGINNING WORK. (REV 10-22-98) (11-5-98) (1-10) Insert Information Required. Change(s) to: 8-3.3. |
SP0080303C | Only when called for by the District Construction Engineer. *Contracts Office must be notified. |
|
|
PROSECUTION OF WORK - PARTNERING. (REV 3-4-98) (FA 5-26-98) (1-10) Insert Information Required. Change(s) to: 8-3.3. |
SP0080306 | 999-16* *Contracts Office must be notified |
|
|
PROSECUTION OF WORK - DISPUTES REVIEW BOARD. (REV 11-19-02) (FA 3-5-03) (1-10) Change(s) to: 8-3. |
SP0080307DRB | 999-20* *Contracts Office must be notified |
|
|
PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD. (REV 4-1-02) (FA 12-12-02) (1-10) Change(s) to: 8-3. |
SP0080307RDRB | Jobs without 999-20 | |
|
PROSECUTION OF WORK - STATEWIDE DISPUTES REVIEW BOARD. (REV 6-23-03) (FA 8-1-03) (1-10) Change(s) to: 8-3. |
SP0080307SDRB | Jobs with Asphalt Pavement, concrete pavement, landscape installation,or performance turf | |
|
PROSECUTION AND PROGRESS. (REV 8-1-00) (1-10) Change(s) to: 8-4.1, 8-7.3.1. |
SP0080401LS | Lump Sum Projects | |
|
LIMITATIONS OF OPERATIONS - FENCING. (REV 6-17-04) (FA 7-13-04) (1-10) Change(s) to: 8-4.8. |
SP0080408 | Jobs on Limited Access Highways | |
|
HAZARDOUS OR TOXIC WASTE - MERCURY-CONTAINING DEVICES AND LAMPS. (REV 11-6-95) (FA 12-27-95) (1-10) Insert Information Required. Change(s) to: 8-4.9. |
SP0080409 | Jobs with Lighting* | |
|
COMPUTATION OF CONTRACT TIME. (REV 12-22-98) (FA 1-19-99) (1-10) Insert Information Required. Change(s) to: 8-7.1. |
SP0080701A | Use when requested by proper authority, (must be modified) | |
|
COMPUTATION OF CONTRACT TIME. (REV 7-24-96) (FA 9-3-96) (1-10) Change(s) to: 8-7.1. |
SP0080701AB | A+B Bidding. (Use with proper authority). Use with SP0020501AB, SP0030100AB,SP0030203 and SP0081300AB | |
|
COMPUTATION OF CONTRACT TIME. (REV 2-14-94) (1-10) Insert Information Required. Change(s) to: 8-7.1. |
SP0080701B | Only when called for (must be modified) | |
|
COMPUTATION OF CONTRACT TIME. (REV 12-22-98) (FA 2-1-99) (1-10) Change(s) to: 8-7.1. |
SP0080701C | Use when requested by proper authority | |
|
DAMAGE RECOVERY. (REV 2-4-04) (1-10) Insert Information Required. Change(s) to: Section 8. |
SP0081300 | Use when requested by proper authority (Do not use with Lane Rental) | |
|
PROSECUTION AND PROGRESS. (REV 7-28-97) (1-10) Change(s) to: Section 8. |
SP0081300A | All Jobs with Alternative Bidding. (Use with proper authority | |
|
8-13. Incentive - Disincentive for A+B. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. |
SP0081300AB | A+B Bidding. (Use with proper authority). Use with SP0020501AB, SP0030100AB, SP0030203 and SP0080701AB | |
|
8-13. "Bonus" Payment and Waiver of Contractor Claims. (REV 5-19-04) (FA 7-13-04) (1-05) Insert Information Required. Change(s) to: 8-13. |
SP0081300ABB | A+B Jobs with Bonus (Use with proper authority) | |
|
8-13. " Bonus " Payment and Waiver of Contractor Claims. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. |
SP0081300B | Bonus (Date Specific) (Use with proper authority | |
|
8-13. "Bonus" Payment and Waiver of Contractor Claims. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. |
SP0081300BCD | Bonus (Calendar Days) (Use with proper authority | |
|
8-13. Incentive - Disincentive. (REV 7-27-04) (FA 7-28-04) (1-05) Insert Information Required. Change(s) to: 8-13. |
SP0081300ID | Incentive - Disincentive. (Use with proper authority) | |
|
8-13. Incentive - Disincentive for Lane Rental Days. (REV 9-25-03) (FA 12-24-03) (7-04) Insert Information Required. Change(s) to: 8-13. |
SP0081300IDLR | Incentive-Disincentive for Lane Rental Days. (Use with proper authority). Do not use with SP0081300LR or SP0081300LRDR | |
|
8-13. Liquidated Savings for Early Completion. (REV 5-18-99) (FA 6-10-99) (7-00) Insert Information Required. Change(s) to: 8-13. |
SP0081300LQS | Liquated Savings. (Use with proper authority) | |
|
8-13. Pay Adjustment For Fewer-More Lane Rental Days. (REV 4-29-97) (FA 5-7-97) (7-00) Insert Information Required. Change(s) to: 8-13. |
SP0081300LR | Lane Rental. (Use with proper authority) Use with SP0020501LR, SP0030100LR and SP0081300LRDR. | |
|
8-13. Damage Recovery. (REV 9-25-03) (FA 12-24-03) (7-04) Insert Information Required. Change(s) to: 8-13. |
SP0081300LRDR | Lane Rental. (Use with proper authority) Use with SP0020501LR, SP0030100LR and SP0081300LR. | |
|
8-13. "Bonus" Payment and Waiver of Contractor Claims. (REV 4-12-06) (FA 4-25-06) (1-07) Insert Information Required. Change(s) to: 8-13. |
SP0081300MB | Milestone Bonus (Use with proper authority). Do not use with SP0081300B or SP0081300BCD | |
|
8-13. Incentive - Disincentive. (REV 2-9-06) (FA 4-25-06) (1-07) Insert Information Required. Change(s) to: 8-13. |
SP0081300MID | Milestone Incentive-Disincentive. (Use with proper authority). Do not use with SP0081300ID | |
|
MEASUREMENT AND PAYMENT. (REV 2-18-10) (FA ) (7-10) Change(s) to: 9-1.3, 9-2, 9-3, 9-5.5.2, 9-9, 9-11. |
SP0090103LS | Lump Sum Projects. Do not use with SP0090103SLLS. | |
|
MEASUREMENT AND PAYMENT. (REV 10-12-09) (FA 11-9-09) (7-10) Change(s) to: 9-1.3, 9-2, 9-3, 9-5.1, 9-8.1, 9-9. |
SP0090103SLLS | Streamline Plan Lump Sum Projects less than $2,000,000 and less than 2,000 tons of asphalt. Do not use with SP0090103LS. | |
|
MEASUREMENT AND PAYMENT. (REV 10-13-09) (FA 11-9-09) (7-10) Change(s) to: 9-1.3.2, 9-2.1.1.2, 9-3.2.3, 9-5.1, 9-8.1, 9-9. |
SP0090103SLPQ | Streamline Plan Quantity Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
MEASUREMENT AND PAYMENT. (REV 10-29-08) (FA 1-16-09) (1-10) Change(s) to: 9-5.1, 9-5.4, 9-9. |
SP0090501DC | District Let Contracts. Excluding Lump Sum Projects | |
|
PARTIAL PAYMENTS - WITHHOLDING PAYMENT. (REV 2-11-09) (FA 6-16-09) (1-10) Change(s) to: 9-5.3. |
SP0090503ES | All American Recovery and Reinvestment Act of 2009 Jobs | |
|
MEASUREMENT AND PAYMENT - ACCEPTANCE AND FINAL PAYMENT DOCUMENTS. (REV 6-10-09) (FA 6-16-09) (1-10) Change(s) to: 9-8.1. |
SP0090801ES | All American Recovery and Reinvestment Act of 2009 Jobs. Do not use with SP0090801ESSL. | |
|
MEASUREMENT AND PAYMENT - ACCEPTANCE AND FINAL PAYMENT DOCUMENTS. (REV 10-21-09) (FA 11-10-09) (7-10) Change(s) to: 9-8.1. |
SP0090801ESSL | Streamline ARRA of 2009 Projects less than $2,000,000 and less than 2,000 tons of asphalt. Do not use with SP0090801ES | |
|
ENGINEER'S FIELD OFFICE. (REV 2-17-10) (7-10) Change(s) to: 109. |
SP1090000 | 109-71 Items | |
|
REMOVAL OF EXISTING BULKHEAD. (REV 7-10-95) (FA 6-21-99) (1-10) Change(s) to: 110-1, 110-11.8, 110-12.7. |
SP1100100 | 110-73 Items | |
|
REMOVAL OF EXISTING STRUCTURES - STRUCTURES TO BE REMOVED. (REV 9-10-07) (FA 2-15-08) (1-10) Insert Information Required. Change(s) to: 110-6.1. |
SP1100601 | Use when requested by proper authority (Must have signed agreement with Local Agency). | |
|
REMOVAL OF EXISTING STRUCTURES. (REV 5-13-05) (FA 8-18-05) (1-10) Change(s) to: 110-6.6. |
SP1100606 | Use when areas of Asbestos Abatement are identified in the Plans | |
|
MATERIAL FOR REEF ESTABLISHMENT. (REV 7-10-95) (FA 6-21-99) (1-10) Change(s) to: 110-11.2, 110-12.7. |
SP1101102 | 110-84 | |
|
EXCAVATION - INDENTIFIED AREAS OF CONTAMINATION. (REV 1-3-94) (FA 6-21-99) (1-10) Change(s) to: 120-1. |
SP1200100A | Use when contaminated areas are delineated in the plans | |
|
FILL GRAVEL. (REV 3-11-96) (1-10) Change(s) to: 120-1, 120-12, 120-13, 120-14.4. |
SP1200100B | 120-72 plan details required | |
|
EXCAVATION AND EMBANKMENT - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (7-10) Change(s) to: 120-10.3.1. |
SP1201003SL | Streamline Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
EXCAVATION FOR STRUCTURES AND PIPE - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (7-10) Change(s) to: 125-9.3.1. |
SP1250903SL | Streamline Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
FILL SAND. (REV 1-3-94) (1-10) Change(s) to: 142. |
SP1420000 | 142-70 (Plans to cover Material and Placement) | |
|
STABILIZED SUBBASE UNDER CONCRETE (REV 1-3-94) (1-10) Change(s) to: 160-3. |
SP1600300 | Only when called for | |
|
STABILIZING - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (7-10) Change(s) to: 160-4.2.4. |
SP1600402SL | Streamline Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
PREDESIGNED STABILIZED SUBGRADE. (REV 3-12-07) (FA 3-14-07) (1-10) Change(s) to: 161. |
SP1610000 | Non-Traffic and Shoulder-Only Construction. Do Not Use on Widening Projects | |
|
ROCK BASE - ACCEPTANCE PROGRAM (REV 9-16-09) (FA 11-9-09) (7-10) Change(s) to: 200-7.2.2 |
SP2000702SL | Streamline Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
GRADED AGGREGATE BASE.
(REV 8-8-07) (1-10)
Change(s) to: 204. |
SP2040000 | Non-FA Jobs with 285 Items | |
|
MILLING OF EXISTING ASPHALT PAVEMENT. (REV 8-31-99) (FA 2-14-00) (1-10) Insert Information Required. Change(s) to: 327-1, 327-6. |
SP3270100 | When the plans provide a location for stockpiling milled material.Insert quantity to be retained. Use all, tons, cubic yards | |
|
MILLING OF EXISTING ASPHALT PAVEMENT. (REV 12-1-93) (1-10) Change(s) to: 327-2. |
SP3270200 | Use when requested by districts | |
|
PORTLANS CEMENT CONCRETE - ACCEPTANCE SAMPLING AND TESTING (REV 9-16-09) (FA 11-9-09) (7-10) Change(s) to: 346-9.2. |
SP3460902SL | Streamline Projects less than $2,000,000 and less than 2,000 tons of asphalt. | |
|
COMPOSITE PANEL SUPPORT REPAIR. (REV 12-10-93) (1-10) Change(s) to: 400. |
SP4000000 | 400-128 | |
|
PRECAST BULKHEAD PANELS. (REV 7-10-95) (1-10) Change(s) to: 400-22.1, 400-23.9. |
SP4002201 | 400-72 (requires plan details) | |
|
REPLACE GRATES. (REV 2-3-94) (1-10) Change(s) to: 425-1, 425-8. |
SP4250100 | 425-82 (requires plan details) | |
|
DEEP DRAINAGE WELLS. (REV 11-9-93) (1-10) Change(s) to: 444. |
SP4440000 | 444-70 Items 444-71 Items |
|
|
EPOXY JOINTING OF PRECAST SEGMENTS - CONTACT TIME (OPEN TIME) AND CONTACT STRENGTH. (REV 1-29-10) (7-10) Change(s) to: 453-4.5.2 |
SP4530405 | All Precast Segmental Bridge Jobs. | |
|
STRUCTURES FOUNDATIONS - PILING.
(REV 8-6-09) (FA 8-27-09) (1-10)
Change(s) to: 455-5.10, 455-5.11, 455-5.12, 455-7.2, 455-7.8, 455-11, 455-12. |
SP4550510A | All Bridge projects with square, prestressed concrete pile foundations, with test piles | |
|
STRUCTURES FOUNDATIONS - PILING.
(REV 8-6-09) (FA 8-27-09) (1-10)
Change(s) to: 455-5.10, 455-5.11, 455-5.14, 455-7.2, 455-7.8, 455-11, 455-12. |
SP4550510B | All Bridge projects with square, prestressed concrete pile foundations, without test piles | |
|
INTEGRAL PILE JACKETS.
(REV 6-20-08) (FA 6-26-08) (1-10)
Change(s) to: 457. |
SP4570000 | 457-70 | |
|
BARRIER WALL REMOVAL (CONCRETE). (REV 7-10-95) (1-10) Change(s) to: 521-1. |
SP5210100 | 521-73 (plan details required) | |
|
OPAQUE VISUAL BARRIER. (REV 4-13-94) (1-10) Change(s) to: 539. |
SP5390000 | 539-80 Items | |
|
FENCING. (REV 1-6-98) (1-10) Change(s) to: 550-2, 550-3.5, 550-6.2. |
SP5500200 | Type A fencing on non-NHS Projects only | |
|
PAINTED PAVEMENT MARKINGS. (REV 1-22-10) (FA 1-25-10) (7-10) Change(s) to: 710-2, 710-4.3, 710-4.5. |
SP7100200 | Maintenance Projects Only | |
|
MOTORIST AID CALL BOX RELOCATION. (REV 11-30-00) (FA 2-2-01) (1-10) Change(s) to: 714. |
SP7140000 | 714-1-500 | |
|
TRAFFIC MONITORING SITE VEHICLE SENSOR (CLASS II). (REV 6-16-99) (FA 7-20-99) (1-10) Change(s) to: 741. |
SP7410000 | 741-70 Items | |
|
TRAFFIC MONITORING SITE VEHICLE SPEED/CLASSIFICATION UNIT. (REV 6-16-99) (FA 7-20-99) (1-10) Change(s) to: 743. |
SP7430000 | 743-70 Items | |
|
TRAFFIC MONITORING SITE SOLAR POWER UNIT. (REV 6-16-99) (FA 7-20-99) (1-10) Change(s) to: 744. |
SP7440000 | 744-70 Items | |
|
TRAFFIC MONITORING SITE INDUCTIVE LOOP ASSEMBLY. (REV 10-25-01) (FA 12-21-01) (1-10) Change(s) to: 745. |
SP7450000 | 745-70 Items | |
|
TRAFFIC MONITORING SITE CABINET. (REV 5-6-08) (FA 10-14-08) (1-10) Change(s) to: 746. |
SP7460000 | 746-7A-BCD | |
|
TRAFFIC MONITORING SITE MODEM. (REV 5-20-99) (FA 7-20-99) (1-10) Change(s) to: 747. |
SP7470000 | 747-70 Items | |
|
GENERAL REQUIREMENTS FOR THE EVALUATION OF TRAFFIC MONITORING SITE
EQUIPMENT AND MATERIALS. (REV 5-12-99) (FA 7-20-99) (1-10) Change(s) to: 748. |
SP7480000 | Jobs with Traffic Monitoring Sites | |
|
TRAFFIC MARKING MATERIALS. (REV 1-21-10) (FA 1-25-10) (7-10) Change(s) to: 971-4. |
SP9710400 | Maintenance Projects Only. | |
|
TRANSPORTATION ENHANCEMENT PROJECTS. (REV 8-6-96) (FA 12-10-96) (1-10) Change(s) to: 120-9.2, 200-7.2, 330-11.3, 330-13. |
SPXENHANCE | For Non-vehicular Asphalt Construction such as Multi-Use Trails | |
| Supplemental Specifications | SS0000001 | All Jobs | |
|
002 PREQUALIFICATION OF BIDDERS.
(REV 6-2-09) (FA 6-4-09) (1-10)
Change(s) to: 2-1. |
SS0020100 | All Jobs | |
|
003 EXECUTION OF CONTRACT BOND.
(REV 8-10-09) (FA 8-13-09) (1-10)
Change(s) to: 3-5.1, 3-6, 3-7. |
SS0030600 | All Jobs | |
|
004 SCOPE OF WORK.
(REV 7-28-09) (FA 7-30-09) (1-10)
Change(s) to: 4-3.9.6, 4-6 |
SS0040309 | All Jobs | |
|
006 DEFECTIVE MATERIALS. (REV 8-5-09) (FA 8-11-09) (1-10) Change(s) to: 6-4. |
SS0060400 | All Jobs | |
|
007 LEGAL REQUIREMENTS AND RESPONSIBILITY TO
THE PUBLIC. (REV 6-24-09) (FA 8-27-09) (1-10) Change(s) to: 7.1.4, 7-11.4, 7-25. |
SS0070104 | All Jobs | |
|
008 PROSECUTION AND PROGRESS. (REV 9-18-09) (FA 11-9-09) (7-10) Change(s) to: 8-3.3, 8-7.3.2. |
SS0080303 | All Jobs | |
|
009 MEASUREMENT AND PAYMENT. (REV 2-8-10) (FA 2-17-10) (7-10) Change(s) to: 9-2.1.1. |
SS0090211 | All Jobs Excluding Lump Sum | |
|
102
MAINTENANCE OF TRAFFIC. (REV 8-4-09) (FA 8-11-09) (1-10) Change(s) to: 102-2, 102-5, 102-7, 102-9, 102-10,102-11, 102-13. |
SS1020000 | All Jobs | |
|
104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION
AND WATER POLLUTION. (REV 11-24-09) (FA 12-28-09) (7-10) Change(s) to: 104-6, 104-7, 104-8, 104-9, 104-10. |
SS1040600 | All Jobs | |
|
105 CONTRACTOR QUALITY CONTROL. (REV 12-22-09) (FA 1-4-10) (7-10) Change(s) to: 105-3, 105-5, 105-6, 105-8, 104-9, 104-10. |
SS1050302 | All Jobs | |
|
107 LITTER REMOVAL AND MOWING. (REV 12-17-09) (FA 1-27-10) (7-10) Change(s) to: New Section after 105.. |
SS1070000 | All Jobs | |
|
110 CLEARING AND GRUBBING. (REV 5-29-09) (FA 7-15-09) (1-10) Change(s) to 110-6.2.1. |
SS1100602 | All Jobs | |
|
120 EXCAVATION AND EMBANKMENT. (REV 8-5-09) (FA 8-13-09) (1-10) Change(s) to: 120-8.1, 120-10.1.7, 120-10.3.1. |
SS1200800 | All Jobs | |
|
125 EXCAVATION FOR STRUCTURES AND PIPE. (REV 6-3-09) (FA 8-13-09) (1-10) Change(s) to: 125-9.1. |
SS1250901 | All Jobs | |
|
160 STABILIZATION - DEPARTMENT VERIFICATION TESTS.. (REV 12-29-09) (FA 2-17-10) (7-10) Change(s) to: 160-4.3.2. |
SS1600403 | All Jobs | |
|
234 SUPERPAVE ASPHALT BASE-THICKNESS REQUIREMENTS. (REV 7-29-09) (FA 8-11-09) (1-10) Change(s) to: 234-8.1. |
SS2340801 | All Jobs | |
|
300 APPLICATION OF TACK COAT - RATE OF APPLICATION. (REV 7-29-09) (FA 8-11-09) (1-10) Change(s) to: 300-8.4. |
SS3000804 | All Jobs | |
|
320 HOT BITUMINOUS MIXTURES - PLANT, METHODS AND EQUIPMENT.
(REV 1-8-10) (FA 2-2-10) (7-10)
Change(s) to: 320-2.2, 320-5.1.2, 320-5.3.1. |
SS3200202 | All Jobs | |
|
327 MILLING OF EXISTING ASPHALT PAVEMENT - CONSTRUCTION. (REV 1-26-10) (FA 2-2-10) (7-10) Change(s) to: 327.3. |
SS3270300 | All Jobs | |
|
330 HOT BITUMINOUS MIXTURES - GENERAL CONSTRUCTION REQUIREMENTS.
(REV 1-26-10) (FA 2-2-10) (7-10)
Change(s) to: 330-2, 330-3, 330-4, 330-6, 330-7, 330-8, 330-9 330-12. |
SS3300000 | All Jobs | |
|
334 SUPERPAVE ASPHALT CONCRETE. (REV 2-8-10) (FA 2-17-10) (7-10) Change(s) to:334-2, 334-3, 334-4, 334-5, 334-5, 334-8. | SS3340000 | All Jobs | |
|
336 ASPHALT RUBBER BINDER.
(REV 1-14-10) (FA 2-2-10) (7-10)
Change(s) to: 336-1, 336-2, 336-3, 336-5, 336-6, 336-7, 336-8. |
SS3360000 | All Jobs | |
|
337 ASPHALT CONCRETE FRICTION COURSES. (REV 1-11-10) (FA 2-2-10) (7-10) Change(s) to: 337-2, 337-3, 337-6, 337-7. |
SS3370000 | All Jobs | |
|
338 VALUE ADDED ASPHALT PAVEMENT. (REV 2-12-10) (FA 2-17-10) (7-10) Change(s) to: 338. |
SS3380100 | All Jobs | |
|
341 ASPHALT RUBBER MEMBRANE INTERLAYER. (REV 7-29-09) (FA 8-11-09) (1-10) Change(s) to: 341-4, 341-5. |
SS3410400 | All Jobs | |
|
346 PORTLAND CEMENT CONCRETE. (REV 1-29-10) (FA 2-1-10) (7-10) Change(s) to: 346-3, 346-4, 346-6, 346-7, 346-8, 346-9, 346-12. |
SS3460301 | All Jobs | |
|
355 VALUE ADDED PORTLAND CEMENT CONCRETE PAVEMENT. (REV 2-12-10) (FA 2-17-10) (7-10) Change(s) to: 355-1, 355-4, 355-5. |
SS3550100 | All Jobs | |
|
400 CONCRETE STRUCTURES. (REV 10-12-09) (FA 11-20-09) (7-10) Change(s) to: 400-7, 400-15, 400-21. |
SS4000713 | All Jobs | |
|
407 THREE-SIDED PRECAST CULVERT. (REV 12-7-07) (FA 1-10-08) (1-10) Change(s) to: 407. |
SS4070000 | 407-1 Items | |
|
415 REINFORCING STEEL - BAR SUPPORTS. (REV 1-15-10) (FA 1-21-10) (7-10) Change(s) to: 415-5.13. |
SS4150513 | All Jobs | |
|
443 FRENCH DRAINS. (REV 9-24-09) (FA 10-6-09) (7-10) Change(s) to: 443-2.3, 443-5. |
SS4430203 | All Jobs | |
|
446 EDGEDRAIN (DRAINCRETE) - CONTROL OF QUALITY. (REV 1-15-10) (FA 2-19-10) (7-10) Change(s) to: 446-3. |
SS4460300 | All Jobs | |
|
450 PRECAST PRESTRESSED CONCRETE CONSTRUCTION - CONCRETE PLACEMENT.
(REV 6-5-09) (FA 6-10-09) (1-10)
Change(s) to: 450-10.3.2.3. |
SS4501003 | All Jobs | |
|
452 PRECAST SEGMENTAL BRIDGE CONSTRUCTION. (REV 6-4-07) (FA 6-28-07) (1-10) Change(s) to: 452. |
SS4520000 | All Precast Segmental Bridge Jobs | |
|
453 EPOXY JOINTING OF PRECAST SEGMENTS. (REV 1-28-03) (FA 2-6-03) (1-10) Change(s) to: 453. |
SS4530000 | Jobs with Segmental Bridges | |
|
455 STRUCTURES FOUNDATIONS.
(REV 4-22-09) (FA 6-10-09) (1-10)
Change(s) to: 455-16.4, 455-17.6.1.1. |
SS4551604 | All Jobs | |
|
462 POST-TENSIONING. (REV 9-18-09) (FA 10-6-09) (7-10) Change(s) to: 462. |
SS4620000 | 462 Items | |
|
524 CONCRETE DITCH AND SLOPE PAVEMENT. (REV 8-13-09) (FA 10-6-09) (7-10) Change(s) to: 524 |
SS5240200 | All Jobs | |
|
527 DETECTABLE WARNINGS ON WALKING SURFACES. (REV 4-7-09) (FA 7-10-09) (1-10) Change(s) to: 527. |
SS5270000 | All Jobs | |
|
546 RUMBLE STRIPS. (REV 7-6-09) (FA 8-31-09) (1-10) Change(s) to: 546-2. |
SS5460200 | All Jobs | |
|
560 COATING STRUCTURAL STEEL. (REV 6-11-09) (FA 6-25-09) (1-10)
Change(s) to: 560. |
SS5600000 | All Jobs | |
|
561 COATING EXISTING STRUCTURAL STEEL. (REV 1-27-10) (FA 2-10-10) (7-10) Change(s) to: New Section 561. |
SS5610000 | 561 Items | |
|
563 ANTI-GRAFFITI COATING SYSTEM - DESCRIPTION.
(REV 4-27-09) (FA 5-27-09) (1-10)
Change(s) to: 563. |
SS5630100 | All Jobs | |
|
570 PERFORMANCE TURF. (REV 10-14-09) (FA 12-28-09) (7-10) Change(s) to: 570 |
SS5700000 | All Jobs./td> | |
|
603 GENERAL REQUIREMENTS FOR THE INSTALLATION AND EVALUATION OF TRAFFIC CONTROL SIGNALS AND DEVICES. (REV 1-20-10) (FA 1-28-10) (7-10) Change(s) to: 603 |
SS6030000 | All Jobs. | |
|
608 GUARANTIES FOR TRAFFIC CONTROL SIGNALS AND DEVICES. (REV 1-20-10) (FA 1-28-10) (7-10) Change(s) to: 608 |
SS6080000 | All Jobs. | |
|
611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES. (REV 11-10-09) (FA 1-28-10) (7-10) Change(s) to: 611 |
SS6110000 | All Jobs. | |
|
650 VEHICULAR SIGNAL ASSEMBLIES. (REV 6-17-09) (FA 6-18-09) (1-10) Change(s) to: 650-3.7. |
SS6500307 | All Jobs | |
|
690 REMOVAL OF EXISTING TRAFFIC CONTROL SIGNALS AND DEVICES. (REV 1-20-10) (FA 1-28-10) (7-10) Change(s) to: 690 |
SS6900000 | All Jobs. | |
|
700 HIGHWAY SIGNING. (REV 6-29-09) (FA 7-1-09) (1-10) Change(s) to: 700. |
SS7000000 | All Jobs | |
|
Mandatory Revision No.1 (REV 5-1-09) (FA 6-24-09) (1-10)
Change(s) to : 701-2.1, 701-4, 701-5, 701-7, 701-8. |
|||
|
Mandatory Revision No.1 701 AUDIBLE AND VIBRATORY PAVEMENT MARKINGS. (REV 4-28-10) (FA 5-7-10) (8-10)
Change(s) to : 701-2.1, 701-4, 701-5, 701-7, 701-8. |
SS7010000 | 701 Items | |
|
Mandatory Revision No.1 702 Wet Weather Pavement Markings (REV 4-28-10) (FA 5-7-10) (8-10)
Change(s) to : New Section. |
SS7020000 | 702 Items | |
|
709 TRAFFIC STRIPES AND MARKINGS - TWO REACTIVE COMPONENTS. (REV 9-24-09) (FA 12-2-09) (7-10) Change(s) to: 709-2, 709-3, 709-4, 709-6, 709-7. |
SS7090000 | All Jobs | |
|
710 PAINTED PAVEMENT MARKINGS. (REV 7-9-09) (FA 7-20-09) (1-10) Change(s) to: 710-2, 710-4.1, 710-4.1.1, 710-4.3. |
SS7100200 | All Jobs | |
|
711 THERMOPLASTIC TRAFFIC
STRIPES AND MARKINGS.
(REV 5-6-09) (FA 6-24-09) (1-10)
Change(s) to: 711-2.1.2, 711-2.1.3, 711-4.1, 711-4.3, 711-7. |
SS7110201 | All Jobs | |
|
713 PERMANENT TAPE
STRIPES AND MARKINGS.
(REV 5-6-09) (FA 6-25-09) (1-10)
Change(s) to: 713-2, 713-4.1, 713-7. |
SS7130200 | All Jobs | |
|
715 HIGHWAY LIGHTING SYSTEM. (REV 1-22-10) (FA 2-10-10) (7-10) Change(s) to: 715-1, 715-16. |
SS7150100 | All Jobs | |
|
780 INTELLIGENT TRANSPORTATION SYSTEMS-GENERAL
REQUIREMENTS. (REV 8-7-06) (FA 8-15-06) (1-10) Change(s) to: 780. |
SS7800000 | All ITS Jobs | |
|
781 INTELLIGENT TRANSPORTATION SYSTEMS-MOTORIST
INFORMATION SYSTEMS. (REV 1-20-10) (FA 1-27-10) (7-10) Change(s) to: 781-3, 781-4, 781-5. |
SS7810000 | 781 Items | |
|
782 INTELLIGENT TRANSPORTATION SYSTEMS-VIDEO
EQUIPMENT. (REV 9-29-09) (FA 11-24-09) (7-10) Change(s) to: 782-1, 782-2. |
SS7820000 | 782 Items | |
|
783 INTELLIGENT TRANSPORTATION SYSTEMS-FIBER
OPTIC CABLE AND INTERCONNECT. (REV 1-21-10) (FA 1-27-10) (7-10) Change(s) to: 783-1, 783-2, 783-3. |
SS7830000 | 783 Items | |
|
784 INTELLIGENT TRANSPORTATION SYSTEMS-NETWORK
DEVICES. (REV 2-9-10) (FA 2-18-10) (7-10) Change(s) to: 784-1, 784-2, 784-3. |
SS7840000 | 784 Items | |
|
785 INTELLIGENT TRANSPORTATION SYSTEMS-INFRASTRUCTURE. (REV 6-22-09) (FA 8-11-09) (1-10) Change(s) to: 785. |
SS7850000 | 785 Items | |
|
786 INTELLIGENT TRANSPORTATION SYSTEMS-VEHICLE
DETECTION AND DATA COLLECTION. (REV 1-28-09) (FA 2-4-09) (1-10) Change(s) to: 786. |
SS7860000 | 786 Items | |
|
901 COARSE AGGREGATE. (REV 12-15-09) (FA 12-21-09) (7-10) Change(s) to: 901-1.4 |
SS9010104 | All Jobs | |
|
916 BITUMINOUS MATERIALS. (REV 1-14-10) (FA 2-2-10) (7-10) Change(s) to: 916-1.1, 916-1.2, 916-5. |
SS9160000 | All Jobs | |
|
919 GROUND TIRE RUBBER FOR USE IN ASPHALT RUBBER BINDER. (REV 6-22-09) (FA 6-25-09) (1-10) Change(s) to: 919-3. |
SS9190300 | All Jobs | |
|
926 EPOXY COMPOUNDS. (REV 1-4-10) (FA 1-14-10) (7-10) Change(s) to: 926-1, 926-2.2. |
SS9260100 | All Jobs | |
|
932 NONMETALLIC ACCESSORY MATERIALS FOR CONCRETE PAVEMENT AND CONCRETE STRUCTURES. (REV 9-22-09) (FA 11-20-09) (7-10) Change(s) to: 932-1. |
SS9320102 | All Jobs | |
|
938 POST-TENSION GROUT.
(REV 5-1-09) (FA 5-19-09) (1-10)
Change(s) to: 938. |
SS9380000 | 462 Items | |
|
962 STRUCTURAL STEEL
AND MISCELLANEOUS METAL ITEMS (OTHER THAN ALUMINUM). (REV 6-26-09) (FA 7-10-09) (1-10) Change(s) to: 962-1.2, 962-8.4.2. |
SS9620102 | All Jobs | |
|
Mandatory Revision No.1 (REV 6-25-09) (FA 6-29-09) (1-10)
Change(s) to: 971 |
|||
|
Mandatory Revision No.1 971 TRAFFIC MARKING MATERIALS. (REV 5-6-10) (FA 5-11-10) (8-10)
Change(s) to: 971 |
SS9710000 | All Jobs | |
|
973 STRUCTURAL PLASTICS. (REV 5-11-09) (FA 6-10-09) (1-10) Change(s) to: 973. |
SS9730000 | All Jobs | |
|
975 STRUCTURAL COATING
MATERIALS.
(REV 6-11-09) (FA 6-25-09) (1-10)
Change(s) to: 975. |
SS9750000 | All Jobs | |
|
987 PREPARED SOIL LAYER MATERIALS. (REV 1-15-10) (FA 2-17-10) (7-10) Change(s) to: 987-1. |
SS9870100 | All Jobs | |
|
990 TEMPORARY TRAFFIC CONTROL DEVICE MATERIALS. (REV 8-3-09) (FA 8-11-09) (1-10)
Change(s) to: 990-2, 990-3.1, 990-4.1, 990-4.10, 990-4.11, 990-5, 990-7.1, 990-8. |
SS9900202 | All Jobs | |
|
993 OBJECT MARKERS AND DELINEATORS. (REV 7-9-09) (FA 7-20-09) (1-10) Change(s) to: 993-1.4, 993-2.3.1. |
SS9930104 | All Jobs | |
|
994 RETROREFLECTIVE AND NONREFLECTIVE SHEETING FOR TRAFFIC CONTROL DEVICES. (REV 2-8-10) (FA 2-10-10) (7-10) Change(s) to: 994. |
SS9940000 | All Jobs | |
|
TECHNICAL SPECIAL PROVISIONS.
The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package.
Insert # ________ |
TSPs | Jobs with TSPs | |