July 2003 Workbook

Specifications and Estimates

Implemented Modifications to the 2003 Standard Specifications

July 2003Workbook

for Lettings Effective July 2003 - December 2003


Special Provisions - Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.

Supplemental Specifications - Additions or revisions to the Standard Specifications.

Change Table - Shows all changes made to the Specifications within this workbook.

History of Revisions - To review the History of revisions for this Workbook.



Note: These files are in Adobe Acrobat (PDF) format.

File size ranges from 9 kb to 279 kb.

SPECIAL PROVISIONS SP0000001 All Jobs
INTENT AND SCOPE.

ARTICLE 4-1 (Page 19) is expanded by the following:
The Improvements under this Contract consist of (Place description here).

The summary of pay items for this project is listed in the plans.
Insert # ________

The summary of pay items for this project is listed in the plans.
D0040002 All Jobs, except Lump Sum
INTENT AND SCOPE.

ARTICLE 4-1 (Page 18) is deleted and the following substituted:

Insert # _________
D00401LS All Lump Sum Projects
(REV 8-22-96) (FA 9-3-96) (7-00)
For this Contract, the Department will reject any bid in which the bidder submits proposed Contract time in excess of _________ calendar days.

Insert # _________
D0040091 A+B Bidding. (Use with proper authority). Use with D00200AB, D00300AB, D00800A and D00800AB
(REV 2-8-94) (7-00)

It is anticipated that construction by others will be underway at each end and within this project during the life of this Contract. Coordinate construction operations with those of other Contractors as necessary.
D0040010 When other Contractors are working in the vicinity
DEFINITIONS.
(REV 12-30-94) (FA 5-26-95) (7-00)

ARTICLE 1-3 (Pages 2-10). The definition of Controlling Work Items is deleted and the following substituted:
D0010013 CPM Jobs 
PROPOSAL REQUIREMENTS AND CONDITIONS.
(REV 7-27-00) (1-03)

ARTICLE 2-2 (of the Supplemental Specifications). Beginning with the third paragraph to the end of Article 2-2, the text is deleted.
D00201DC All District Let and Maintenance Contracts
EXAMINATION OF PLANS, SPECIFICATIONS, SPECIAL PROVISIONS AND SITE OF WORK.
(REV 4-19-99) (1-02)

ARTICLE 2-4 (of the Supplemental Specifications) is expanded by the following:

Insert # __________
D0020024 All Jobs, (add a phone number or e-mail address)
PREPARATION OF PROPOSALS.
(REV 11-5-97) (FA 1-25-98) (7-00)

SUBARTICLE 2-5.1 (of the Supplemental Specifications) is expanded as follows:
D00200AB 999-10, 2999-10; A+B Bidding. (Use with proper authority). Use with D00300AB, D0040091, D00800AB and D008007A 
PREPARATION OF PROPOSALS.
(REV 4-29-97) (FA 5-7-97) (7-00)

SUBARTICLE 2-5.1 (of the Supplemental Specifications) is expanded by the following:

Insert # __________
D00200LR 999-5, 2999-5; Lane Rental. (Use with proper authority). Use with D00300LR, D00800LR and D00801LR
AWARD AND EXECUTION OF CONTRACT.
(REV 11-5-97) (FA 1-20-98) (7-00)

ARTICLE 3-1 (of the Supplemental Specifications). The first and second sentences are deleted and the following substituted:

Insert # _________
D00300AB 999-10, 2999-10; A+B Bidding. (Use with proper authority). Use with D00200AB, D0040091,D008007A and D00800AB
AWARD AND EXECUTION OF CONTRACT.
(REV 7-27-00) (1-01)

ARTICLE 3-1 (of the Supplemental Specifications). The first paragraph is expanded by the following:

Insert # _________
D00300DC All District Let and Maintenance Contracts excluding Lump Sum
AWARD AND EXECUTION OF CONTRACT.
(REV 8-1-00) (1-01)

ARTICLE 3-1 (of the Supplemental Specifications). The first paragraph is deleted and the following substituted:
D00300LS Lump Sum Projects
AWARD AND EXECUTION OF CONTRACT.
(REV 4-11-97) (FA 5-7-97) (7-00)

ARTICLE 3-1 (of the Supplemental Specifications). The first and second sentences are deleted and the following substituted:
D00300LR 999-5, 2999-5; Lane Rental. (Use with proper authority). Use with D00200LR, D00800LR and D00801LR 
AWARD AND EXECUTION OF CONTRACT.
(REV 7-26-01) (1-02)

ARTICLE 3-2 (of the Supplemental Specifications) is expanded by the following:

Insert # _________
*Contracts Office must approve
D0032000 When necessary to change standard “Award and Execution”*
AWARD AND EXECUTION OF CONTRACT.
(REV 2-7-97) (7-00)

SUBARTICLE 3-2.1 (of the Supplemental Specifications) is deleted and the following substituted:
D00300003 Bid Average Method (Use with proper authority)
ALTERATION OF PLANS OR OF CHARACTER OF WORK.
(REV 8-1-00) (1-01)

SUBARTICLE 4-3.1 (of the Supplemental Specifications) is deleted and the following substituted:
D00403LS Lump Sum Projects
VALUE ENGINEERING INCENTIVE.
(REV 8-12-96) (FA 7-2-97) (7-00)

SUBARTICLE 4-3.9 (of the Supplemental Specifications) is deleted.
D00400DC District Let Contracts less than $250,000 and all Maintenance Contracts. Excluding Lump Sum
UNFORESEEABLE WORK.
(REV 9-28-98) (7-00)

ARTICLE 4-4 (Page 25) is deleted and the following substituted:
D0040004 999-25
2999-25
MANDATORY REVISION NO. 2

ADD THIS SPECIAL PROVISION


DESIGN STANDARDS (ENGLISH UNITS).
(REV 9-18-03) (10-03)

SUBARTICLE 5-1.1 (Page 26). The "Design Standards" booklet for English Units, dated January 2002, is modified as follows:
D005001E All English Jobs with 548 Pay Items
MANDATORY REVISION NO. 2

ADD THIS SPECIAL PROVISION

ROADWAY AND TRAFFIC DESIGN STANDARDS (METRIC UNITS).
(REV 9-18-03) (10-03)

SUBARTICLE 5-1.1 (Page 26). The "Design Standards" booklet for English Units, dated January 2000, is modified as follows:
D005001M All Metric Jobs with 2548 Pay Items
DESIGN STANDARDS (ENGLISH UNITS).
(REV 10-3-02) (1-03)

SUBARTICLE 5-1.1 (Page 26). The "Design Standards" booklet for English Units, dated January 2002, is modified as follows:
D005011E All English Jobs 
ROADWAY AND TRAFFIC DESIGN STANDARDS (METRIC UNITS).
(REV 8-9-02) (1-03)

SUBARTICLE 5-1.1 (Page 26). The "Design Standards" booklet for English Units, dated January 2000, is modified as follows:
D005011M All Metric Jobs 
CONTROL OF THE WORK.
(REV 3-15-02) (1-03)

SUBARTICLE 5-1.1 (of the Supplemental Specifications) is expanded by the following:
D00500LS Lump Sum Projects
INSPECTION.
(REV 2-10-94) (7-00)

SUBARTICLE 5-9.1 (Page 40) is expanded by the following:

Insert # __________
D0050091 Long bridge jobs (1500 feet [450 m] or longer); modify to suit
CONTROL OF MATERIALS.
(REV 1-9-01) (7-01)

ARTICLE 6-1 (Pages 49 and 50) is expanded by the following new Subarticles:
D00600LS Lump Sum Projects
LAWS TO BE OBSERVED.
(REV 2-1-02) (1-04)

SUBARTICLE 7-1.1 (54 and 56) is expanded by the following:
D0070011 Federal Aid Jobs
ENDANGERED SPECIES.
(REV 2-10-94) (7-00)

SUBARTICLE 7-1.4 (Pages 57 and 58) is expanded by the following:
D0070010 When called for (woodpecker) 
ENDANGERED SPECIES.
(REV 2-27-96) (FA 3-26-96) (1-03)

SUBARTICLE 7-1.4 (Pages 57 and 58) is expanded by the following:
D0070014 When called for (Manatees and/or turtles) 
PERMITS PROCURED BY THE DEPARTMENT.
(REV 8-7-01) (7-02)

SUBARTICLE 7-2.1 (Page 58) is expanded by the following:
D0070021 Jobs with permit(s) procured by DOT
PERMITS PROCURED BY THE CONTRACTOR.
(REV 12-18-00) (1-01)

SUBARTICLE 7-2.1 (Page 58) is expanded by the following:
D0070022 Jobs with buildings
MANDATORY REVISION NO. 1

ADD THIS SPECIAL PROVISION

DISCHARGE TO OR WORK OR STRUCTURES IN NAVIGABLE WATERS OF THE U.S., WATERS OF THE U.S. AND WATERS OF THE STATE.
(REV 6-9-03) (7-03)

SUBARTICLE 7-2.2 (Page 58) is expanded by the following:
D0070002 When DEP Generic Permit is required
MANDATORY REVISION NO. 1

DELETE THIS SPECIAL PROVISION

DISCHARGE TO OR WORK OR STRUCTURES IN NAVIGABLE WATERS OF THE U.S., WATERS OF THE U.S. AND WATERS OF THE STATE.
(REV 2-21-01) (7-03)

SUBARTICLE 7-2.2 (Page 58) is expanded by the following:
D0070002 When NPDES is required
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC.
(REV 1-9-01) (1-04)

SUBARTICLE 7-7.1 (Page 59) is expanded by the following:

Insert # ________
D00700DC District Let Contracts less than $250,000 and all Maintenance Contracts. Excluding Lump Sum
STRUCTURES OVER NAVIGATABLE WATERS.
(REV 2-10-94) (7-00)

ARTICLE 7-8 (Page 61) is expanded by the following:
D0070080 When work platforms are indicated in the permit for construction
USE OF EXPLOSIVES.
(REV 9-26-94) (7-00)

ARTICLE 7-9 (Page 61) is deleted and the following substituted:
D0070008 When explosives are prohibited
UTILITY WORK.
(REV 2-10-94) (7-02)

SUBARTICLE 7-11.6.3 (Pages 65 and 66) is expanded by the following:
D0071164 When no utility work is anticipated 
UTILITY WORK.
(REV 8-27-01) ((7-02)

SUBARTICLE 7-11.6.3 (Pages 65 and 66) is expanded by the following:
D0070116 When there is Utility work
WAGE RATES FOR FEDERAL-AID PROJECTS.
(REV 8-27-99) (FA 11-16-99) (1-03)

ARTICLE 7-16 (of the Supplemental Specifications) is expanded by the following:

Insert # ________
D0070160 All Federal Aid Jobs
DISADVANTAGED BUSINESS ENTERPRISE PROGRAM.
(REV 6-6-02) (FA 7-17-02) (1-03)

SECTION 7 (Pages 54-71) is expanded by the following:
D0070025 All Jobs 
EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS.
(REV 4-25-02) (FA 7-17-02) (1-03)

SECTION 7 (Pages 54-71) is expanded by the following:
D0070026 Non-Federal Aid Projects
ON-THE-JOB TRAINING.
(REV 6-20-02) (1-04)

SECTION 7 (Pages 54-71) is expanded by the following:
D0070027 All Jobs
SUBLETTING CONTRACTS.
(REV 2-14-94) (7-00)

SUBARTICLE 8-1.1 (Page 71) is expanded by the following:
D0080010 Pressure Epoxy Grouting pay item “Injecting and Sealing Prestressed Beams”
PROSECUTION AND PROGRESS.
(REV 8-1-00) (1-03)

SUBARTICLE 8-1.2 (Page 72) is deleted.
D00800LS Lump Sum Projects
SPECIALTY WORK.
(REV 9-28-98) (7-00)

SUBARTICLE 8-1.2 (Page 72). The text is deleted and the following substituted:

Insert #___________
D0080012 For Contracts not normally performed by Road and Bridge Contractors
SUBMISSION OF WORKING SCHEDULE.
(REV 5-30-02) (FA 7-24-02) (1-03)

SUBARTICLE 8-3.2 (Pages 73 and 74) is deleted and the following substituted:
D0080032 Use only when authorized by District Construction Engineer. Do not use with D0080003, D0080039 or D00800DC 
SUBMISSION OF WORKING SCHEDULE.
(REV 5-30-02) (FA 7-24-02) (1-03)

SUBARTICLE 8-3.2 (Pages 73 and 74) is deleted and the following substituted:
D0080039 Use only when authorized by District Construction Engineer. Do not use with D0080003, D0080032 or D00800DC 
SUBMISSION OF WORKING SCHEDULE.
(REV 7-8-02) (FA 7-24-02) (1-03)

SUBARTICLE 8-3.2 (Pages 73 and 74) is deleted and the following substituted:
D0080003 Non CPM Projects.  Do not use with D0080032, D0080039 or D00800DC
PROSECUTION AND PROGRESS.
(REV 2-27-01) (1-03)

SUBARTICLE 8-3.2 (Pages 73 and 74) is deleted.
D00800DC District Let Contracts (including Lump Sum) less than $250,000, and all Maintenance Contracts. Do not use with D0080003, D0080039, D0080048 or D0080050 
PROSECUTION OF WORK - FLEXIBLE START TIME.
(REV 8-2-96) (FA 9-4-96) (1-03)

SUBARTICLE 8-3.3 (Page 74) is deleted and the following substituted:

Insert # ________
*Contracts Office must be notified
D0080083 When called for*
BEGINNING WORK.
(REV 7-10-95) (7-00)

SUBARTICLE 8-3.3 (Page 74). The last sentence is deleted and the following substituted:

Insert # ________
D0080330 When called for by the District Construction Engineer
BEGINNING WORK.
(REV 10-22-98) (FA 11-5-98) (7-00)

SUBARTICLE 8-3.3 (Page 74) is expanded by the following substituted:

Insert # ________
*Contracts Office must be notified
D0080033 Only when called for by the District Construction Engineer
PROSECUTION OF WORK - PARTNERING.
(REV 3-4-98) (FA 5-26-98) (7-00)

ARTICLE 8-3 (Pages 73 and 74) is expanded by the following new Subarticle:

Insert # _______
*Contracts Office must be notified
D0080036 999-16*
2999-16*
PROSECUTION OF WORK - DISPUTES REVIEW BOARD.
(REV 4-15-02) (FA 7-17-02) (1-03)

ARTICLE 8-3 (Pages 73 and 74) is expanded by the following new Subarticle:
D0080037 999-20*
2999-20*
PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD.
(REV 4-1-02) (1-03)

ARTICLE 8-3 (Pages 73 and 74) is expanded by the following new Subarticle:
D0080370 Jobs without 999-20;
2999-20 
LIMITATIONS OF OPERATIONS.
(REV 2-14-94) (7-00)

SUBARTICLE 8-4.1 (Pages 74 and 75) is expanded by the following: Insert#______________
D0080048 When certain night work hours are required. Must be modified to show work hours. (Use when requested by proper authority). Do NOT use with D00800DC 
LIMITATIONS OF OPERATIONS.
(REV 2-14-94) (7-00)

SUBARTICLE 8-4.1 (Pages 74 and 75) is expanded by the following:
D0080050 Modify as appropriate (use only when required). Do NOT use with D00800DC 
HAZARDOUS OR TOXIC WASTE - MERCURY-CONTAINING DEVICES AND LAMPS.
(REV 11-6-95) (FA 12-27-95) (7-00)

SUBARTICLE 8-4.9 (Page 76) is expanded by the following:

Insert # ________ *Insert Hazardous Waste Coordinator and contact number
D0080049 Jobs with Lighting*
COMPUTATION OF CONTRACT TIME.
(REV 7-24-96) (FA 9-3-96) (7-00)

SUBARTICLE 8-7.1 (Page 78) is deleted and the following substituted:
D008007A 999-10, 2999-10; A+B Bidding. (Use with proper authority). Use with D00200AB, D00300AB,D0080091 and D00800AB
COMPUTATION OF CONTRACT TIME.
(REV 12-22-98) (FA 1-19-99) (7-00)

SUBARTICLE 8-7.1 (Page 79) is expanded by the following:

Insert # ________
D0080072 Use when requested by proper authority, (must be modified)
COMPUTATION OF CONTRACT TIME.
(REV 2-14-94) (7-00)

SUBARTICLE 8-7.1 (Page 78) is expanded by the following:

Insert # _______
D0080076 Only when called for (must be modified)
COMPUTATION OF CONTRACT TIME.
(REV 12-22-98) (FA 2-1-99) (7-00)

SUBARTICLE 8-7.1 (Page 78) is expanded by the following:
D0080700 Use when requested by proper authority
PROSECUTION AND PROGRESS.
(REV 7-28-97) (7-00)

SECTION 8 (Pages 71-84) is expanded by the following new Article:
D00800D0 All Jobs with Alternative Bidding. (Use with proper authority)
8-13. Incentive - Disincentive for A+B.
(REV 3-8-99) (7-00)

Insert # _________
D00800AB 999-10, 2999-10; A+B Bidding. (Use with proper authority). Use with D00200AB, D003000AB,D0040091 and D008007A 
8-13. “No Excuse Bonus” Payment and Waiver of Contractor Claims.
(REV 3-8-99) (7-01)

Insert # _________
D0080016 Bonus (Date Specific) (Use with proper authority)
8-13. “No Excuse Bonus” Payment and Waiver of Contractor Claims.
(REV 3-8-99) (7-01)


Insert # _________
D0080D16 Bonus (Calendar Days) (Use with proper authority)
8-13. “No Excuse Bonus” Payment and Waiver of Contractor Claims.
(REV 8-8-02) (1-03)

Insert # _________
D00800MS Milestone Bonus (Use with proper authority). Do not use with D0081600 or D0080D16
8-13. Liquidated Savings for Early Completion.
(REV 5-18-99) (FA 6-10-99) (7-00)

Insert # _________
D0080017 Liquated Savings. (Use with proper authority)
8-13. Incentive - Disincentive.
(REV 3-8-99) (7-00)

Insert # _________
D00800ID Incentive - Disincentive. (Use with proper authority)
8-13. Incentive - Disincentive.
(REV 8-8-02) (1-03)

Insert # __________
D008IDMS Milestone Incentive-Disincentive. (Use with proper authority). Do not use with D00800ID
8-13. Pay Adjustment For Fewer-More Lane Rental Days.
(REV 4-29-97) (FA 5-7-97) (7-00)
D00800LR 999-5, 2999-5; Lane Rental. (Use with proper authority)
8-13. Damage Recovery.
(REV 4-11-97) (FA 5-7-97) (7-00)

Insert # __________
D00801LR 999-5, 2999-5; Lane Rental. (Use with proper authority)
8-13. Incentive - Disincentive for Lane Rental Days.
(REV 8-8-02) (1-03)

Insert # __________
D008IDLR Incentive-Disincentive for Lane Rental Days. (Use with proper authority). Do not use with D00800LR or D00801LR
MEASUREMENT AND PAYMENT.
(REV 6-7-02) (1-03)

SUBARTICLE 9-1.3 (of the Supplemental Specifications) is deleted and the following substituted:
D00900LS Lump Sum Projects
MEASUREMENT AND PAYMENT.
(REV 5-7-97) (FA 7-2-97) (1-03)

SUBARTICLES 9-2.1.1 and 9-2.1.2 (of the Supplemental Specifications) are deleted.
D00900DC District Let Contracts less than $250,000 and all Maintenance Contracts. Excluding Lump Sum Projects
ACCEPTANCE AND FINAL PAYMENT.
(REV 1-13-03) (7-03)

ARTICLE 9-8 (of the Supplemental Specifications) is deleted and the following substituted: 
D0090008 All Jobs 
MANDATORY REVISION NO. 1

ADD THIS SPECIAL PROVISION

104       PREVENTION, CONTROL AND ABATEMENT OF EROSION AND WATER POLLUTION.
(REV 6-10-03) (7-03)

SUBARTICLE 104-5 (Pages 118 and 119) is deleted and the following substituted:
D1040005 All Jobs
MANDATORY REVISION NO. 1

ADD THIS SPECIAL PROVISION

MAINTENANCE OF EROSION CONTROL.
(REV 6-10-03) (7-03)

SUBARTICLE 104-7.1 (Page 123) is deleted and the following substituted:
D1040071 All Jobs 
ENGINEER’S FIELD OFFICE.
(REV 5-1-02) (FA 5-14-02) (1-03)

PAGE 125. The following new Section is added after Section 104:
D1090000 109-71; 2109-71
REMOVAL OF EXISTING BULKHEAD.
(REV 7-10-95) (FA 6-21-99) (7-00)

ARTICLE 110-1 (of the Supplemental Specifications) is expanded by the following:
D1100073 110-73; 2110-73
REMOVAL AND DISPOSAL OF FENDER SYSTEM.
(REV 3-18-94) (FA 6-21-99) (7-00)

SUBARTICLE 110-6.1 (of the Supplemental Specifications) is expanded by the following:
D1100001 110-71-1; 2110-71-1. Modify to suit
MATERIAL FOR REEF ESTABLISHMENT.
(REV 7-10-95) (FA 6-21-99) (7-00)

SUBARTICLE 110-11.2 (of the Supplemental Specifications) is expanded by the following:
D1100113 110-84; 2110-84
EXCAVATION - INDENTIFIED AREAS OF CONTAMINATION.
(REV 1-3-94) (FA 6-21-99) (1-03)

ARTICLE 120-1 (of the Supplemental Specifications) is expanded by the following:
D1200003 Use when contaminated areas are delineated in the plans
FILL GRAVEL.
(REV 3-11-96) (7-00)

ARTICLE 120-1 (of the Supplemental Specifications) is expanded by the following:
D1200123 120-72; 2120-72; plan details required
FILL SAND.
(REV 1-3-94) (7-00)

PAGE 160. The following new Section is added after Section 125:
D1420000 142-70; 2142-70; (Plans to cover Material and Placement)
STABILIZED SUBBASE UNDER CONCRETE PAVEMENT.
(REV 1-3-94) (7-00)

ARTICLE 160-3 (of the Supplemental Specifications) is expanded by the following:
D1600003 Only when called for
STABILIZING-ACCEPTANCE PROGRAM.
(REV 2-4-03) (7-03)

ARTICLE 160-7 (of the Supplemental Specifications) is expanded by the following:
D1600007 160; 2160 Items
ORGANIC SOIL LAYER.
(REV 1-19-00) (FA 1-25-00) (7-00)

PAGE 171. The following new Section is added after Section 162:
D162A0000 162-4; 2162-4
BLANKET MATERIAL.
(REV 10-22-99) (FA 1-20-00) (7-00)

PAGE 171. The following new Section is added after Section 162:
D16300000 163-1; 2163-1
STABILIZED SUBBASE.
(REV 1-3-94) (7-00)

PAGE 180. The following new Section is added after Section 175:
D1800000 180-70; 2180-70
 180-71; 2180-71
MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 8-31-99) (FA 2-14-00) (1-01)

ARTICLE 327-1 (of the Supplemental Specifications). The third paragraph is deleted and the following substituted:

Insert # ________
D3270001 When the plans provide a location for stockpiling milled material.Insert quantity to be retained. Use all, tons, metric tons, cubic yards or cubic meters 
MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 12-1-93) (7-00)

ARTICLE 327-2 (of the Supplemental Specifications) is expanded by the following:
D3270004 Use when requested by districts
SURFACE REQUIREMENTS.
(REV 4-29-98) (FA 5-26-98) (7-02)

ARTICLE 330-12.6 (of the Supplemental Specifications) is expanded by the following new Subarticle:
D3300126 Use on limited access or other high-speed roadways where the design speed is equal to or greater than 50 miles per hour [80 km per hour]
PATCHING PORTLAND CEMENT CONCRETE PAVEMENT.
(REV 2-7-94) (7-00)

PAGE 373. The following new Section is added after 352.
D3540001 354-70; 2354-70 (requires D3530000 also)
COMPOSITE PANEL SUPPORT REPAIR.
(REV 12-10-93) (7-00)

SECTION 400 (of the Supplemental Specifications) is expanded by the following:
D4000003 400-128; 2400-128
PRECAST BULKHEAD PANELS.
(REV 7-10-95) (7-00)

SUBARTICLE 400-22.1 (of the Supplemental Specifications) is expanded by the following:
D4000217 400-72; 2400-72 (requires plan details)
REPLACE GRATES.
(REV 2-3-94) (7-00)

ARTICLE 425-1 (Page 386) is expanded by the following:
D4250010 425-82; 2425-82 
(requires plan details)
DESILTING PIPE.
(REV 6-13-95) (FA 6-21-95) (7-00)

SECTION 430 (of the Supplemental Specifications)  is expanded by the following:
D4300094 430-94; 2430-94 
DESILTING CONCRETE BOX CULVERTS.
(REV 11-9-93) (7-03)

SECTION 430 (of the Supplemental Specifications)  is expanded by the following:
D4300013 430-950; 2430-950 
DEEP DRAINAGE WELLS.
(REV 11-9-93) (7-00)

PAGE 459. The following new Section is added after Section 443:
D440000 444-70; 2444-70
444-71; 2444-71
PRECAST SEGMENTAL BRIDGE CONSTRUCTION.
(REV 1-10-03) (7-03)

PAGE 524. The following new Section is added after Section 451:
D4520000 All Precast Segmental Bridge Jobs
INTEGRAL PILE JACKETS.
(REV 9-12-94) (7-00)

PAGE 598. The following new Section is added after Section 455:
D4570001 457-70; 2457-70
BARRIER WALL REMOVAL (CONCRETE).
(REV 7-10-95) (7-00)

ARTICLE 521-1 (of the Supplemental Specifications) is expanded by the following:
D5210073 521-73; 2521-73 (plan details required)
COLORING CONCRETE SURFACES.
(REV 4-1-99) (7-00)

PAGE 654. The following new Section is added after Section 522:
D5230000 523-70; 2523-70 
OPAQUE VISUAL BARRIER.
(REV 4-13-94) (7-00)

PAGE 672. The following new Section is added after Section 538:
D5390000 539-80; 2539-80 (requires plan details)
FENCING.
(REV 1-6-98) (7-02)

ARTICLE 550-2 (Page 681). The text is deleted and the following substituted:
D5500021 Type A fencing on non-NHS Projects only
COAL TAR-EPOXY COATING OF PERMANENT BULKHEAD SHEET PILES.
(REV 1-3-94) (FA 6-21-99) (7-00)

ARTICLE 560-11 (Pages 691 and 692) is expanded to the following new Subarticle:
D5600115 Only when called for 
GRASSING (BY SEEDING)-WATERING.
(REV 3-10-00) (1-01)

ARTICLE 570-3.6 (Page 700) is deleted and the following substituted: 
D5700036 Seeding Jobs
PLASTIC EROSION MAT.
(REV 1-5-00) (FA 1-12-00) (7-02)

Page 702.The following new Section is added after Section 570:
D5710000 571-1; 2571-1
PAINTING TRAFFIC STRIPES.
(REV 7-25-01) (1-02)

SUBARTICLE 710-4.1 (Page 780) is expanded by the following:
D7100041 Jobs with Traffic Paint
TRAFFIC MONITORING SITE VEHICLE SENSOR (CLASS II).
(REV 6-16-99) (FA 7-20-99) (7-02)

PAGE 797. The following new Section is added after Section 715:
D7410000 741-70;  2741-70
TRAFFIC MONITORING SITE VEHICLE SPEED/CLASSIFICATION UNIT.
(REV 6-16-99) (FA 7-20-99) (7-02)

PAGE 797. The following new Section is added after Section 715:
D7430000 743-70; 2743-70
TRAFFIC MONITORING SITE SOLAR POWER UNIT.
(REV 6-16-99) (FA 7-20-99) (7-02)

PAGE 797. The following new Section is added after Section 715:
D7440000 744-70; 744-70 
TRAFFIC MONITORING SITE INDUCTIVE LOOP ASSEMBLY.
(REV 10-25-01) (FA 12-21-01) (7-02)

PAGE 797. The following new Section is added after Section 715:
D7450000 745-70; 2745-70 (use with D6600062)
TRAFFIC MONITORING SITE CABINET.
(REV 6-21-99) (FA 7-20-99) (7-02)

PAGE 797. The following new Section is added after Section 715:
D7460000 746-7;  2746-7
TRAFFIC MONITORING SITE MODEM.
(REV 5-20-99) (FA 7-20-99) (7-00)

PAGE 797. The following new Section is added after Section 715:
D7470000 747; 2747 Items
GENERAL REQUIREMENTS FOR THE EVALUATION OF TRAFFIC MONITORING SITE EQUIPMENT AND MATERIALS.
(REV 5-12-99) (FA 7-20-99) (7-00)

PAGE 797. The following new Section is added after Section 715:
D7480000 Jobs with Traffic Monitoring Sites
POLE CABLE DISTRIBUTION SYSTEM-QUALIFIED PRODUCTS LIST.
(REV 12-13-02) (7-03)

ARTICLE 992-12 (Pages 957-960) is expanded by the following new Subarticle:
D9920122 Highway Lighting Jobs 
TRANSPORTATION ENHANCEMENT PROJECTS.
(REV 8-6-96) (FA 12-10-96) (1-04)

SUBARTICLE 120-9.2 (of the Supplemental Specifications) is expanded by the following:
DENHANCE For non-vehicular enhancement projects only
 
Supplemental Specifications SS0000001 All Jobs
002        PROPOSAL REQUIREMENTS AND CONDITIONS.
(REV 8-9-02) (FA 9-27-02) (7-03)

SECTION 2 (Pages 10-15) is deleted and the following substituted:
D0020000 All Class I Projects 
003       AWARD AND EXECUTION OF CONTRACT.
(REV 5-22-02) (FA 7-24-02) (1-03)

SECTION 3 (Pages 15-18) is deleted and the following substituted:
D0030000 All Jobs
004       ALTERATION OF PLANS OR OF CHARACTER OF WORK.
(REV 1-10-00) (FA 1-12-00) (7-02)

ARTICLE 4-3 (Pages 18-25) is deleted and the following substituted:
D0040003 All Jobs
005       CONTROL OF WORK.
(REV 4-10-02) (FA 8-19-02) (7-03)

ARTICLE 5-1 (Pages 26-35) is deleted and the following substituted:
D0050001 All Jobs
006      CONTROL OF MATERIALS.
(REV 12-19-01) (FA 1-3-02) (7-03)

 

SUBARTICLE 6-3.2 (Page 50) is expanded by the following new Subarticle:

D0060000 All Jobs
007      LAWS TO BE OBSERVED.
(REV 5-14-02) (FA 12-12-02) (7-03)

ARTICLE 7-1.1 (Pages 54-57) is expanded by the following new Subarticle:
D0070001 All Jobs
007      WAGE RATES FOR FEDERAL-AID PROJECTS.
(REV 8-27-99) (FA 11-16-99) (7-00)

ARTICLE 7-16 (Page 69). The text is deleted and the following substituted:
D0070016 All Federal Aid Jobs
007      SUBMITTAL OF WAGE RATE SUMMARY.
(REV 11-28-00) (FA 2-5-01) (7-02)

 

ARTICLE 7-23 (Page 71) is deleted.

D0070023 All Jobs
008      PROSECUTION AND PROGRESS.
(REV 6-27-02) (FA 10-23-02) (7-03)

 

SUBARTICLE 8-1.1 (Page 71). The first paragraph is deleted and the following substituted:

D0080000 All Jobs
009      MEASUREMENT AND PAYMENT.
(REV 10-24-02) (FA 1-7-03) (7-03)

 

SECTION 9 (Pages 84-101) is deleted and the following substituted: 

D0090000 All Jobs
100     CONSTRUCTION EQUIPMENT - GENERAL REQUIREMENTS.
(REV 12-14-01) (FA 1-4-02) (7-02)

 

SECTION 100 (Pages 102 and 103) is deleted and the following substituted:

D1000000 All Jobs
102      MAINTENANCE OF TRAFFIC.
(REV 1-29-03) (FA 1-31-03) (7-03)

 

SECTION 102 (Pages 104-115) is deleted and the following substituted: 

D1020000 All Jobs
104      CONSTRUCTION REQUIREMENTS - ARTIFICIAL COVERINGS.
(REV 5-8-00) (FA 5-15-00) (1-01)

 

ARTICLE 104-6 (Pages 119-123) is expanded by the addition of the following new Subarticle:

D1040006 104-1; 2104-1
104      BALED HAY OR STRAW.
(REV 5-10-01) (FA 11-9-01) (7-02)

 

SUBARTICLE 104-6.4.9 (Page 121). The text is deleted and the following substituted:

D1040649 All Jobs
MANDATORY REVISION NO.1

 

DELETE THIS SUPPLEMENTAL SPECIFICATION

 

104       MAINTENANCE OF EROSION CONTROL FEATURES.
(REV 2-21-01) (FA 12-19-01) (7-02)

 

SUBARTICLE 104-7.1 (Page 123) is expanded by the following:

D1040071 All Jobs
105       QUALITY CONTROL PLAN.
(REV 12-19-01) (FA 1-4-02) (7-02)

 

PAGE 125. The following new Section is added after Section 104:

D1050000 All Jobs
110       CLEARING AND GRUBBING.
(REV 6-29-01) (FA 7-27-01) (1-02)

 

SECTION 110 (Pages 126-134) is deleted and the following substituted: 

D1100000 110; 2110 Items
120        EXCAVATION AND EMBANKMENT.
(REV 1-14-03) (FA 2-6-03) (7-03)

 

SECTION 120 (Pages 135-150) is deleted and the following substituted:

D1200000 All Jobs
121        FLOWABLE FILL.
(REV 12-20-01) (FA 1-7-02) (7-02)

 

SECTION 121 (Pages 150-152) is deleted and the following substituted: 

D1210000 All Jobs
125         EXCAVATION FOR STRUCTURES AND PIPE.
(REV 1-6-03) (FA 1-14-03) (7-03)

 

SECTION 125 (Pages 152-160) is deleted and the following substituted: 

D1250000 125; 2125 Items
145        GEOSYNTHETIC REINFORCEMENT.
(REV 11-1-99) (FA 11-4-99) (7-03)

 

PAGE 160. The following new Section is added after Section 125:

D1450000 145; 2145 Items 
160       STABILIZING.
(REV 10-17-01) (FA 1-10-02) (7-02)

 

SECTION 160 (Pages 160-165) is deleted and the following substituted: 

D1600000 160; 2160 Items
162       FINISH SOIL LAYER.
(REV 5-28-02) (FA 7-12-02) (1-03)

 

SECTION 162 (Pages 169-171) is deleted and the following substituted:

D1620000 162-3; 2162-3
200      ROCK BASE.
(REV 2-5-03) (FA 2-11-03) (7-03)

 

SECTION 200 (Pages 181-184) is deleted and the following substituted:

D2000000 285; 2285 Items
204      GRADED AGGREGATE BASE.
(REV 10-31-01) (FA 1-3-02) (7-02)

 

ARTICLE 204-6 (Page 186) is deleted and the following substituted:

D2040000 285-7xx; 2285-7xx 
210      REWORKING LIMEROCK BASE.
(REV 12-6-02) (FA 12-13-02) (7-03)

 

ARTICLE 210-3 (Page 187) is deleted and the following substituted:

D2100000 210-1, 2210-1; 210-2;
2210-2 
220      SHAPING AND COMPACTING LOCAL ROCK BASE - BASIS OF PAYMENT.
(REV 12-17-02) (FA 1-7-03) (7-03)

 

ARTICLE 220-7 (Page 189) is deleted and the following substituted:

D2200007 220-1; 2220-1 
230      LIMEROCK STABILIZED BASE.
(REV 12-6-02) (FA 12-13-02) (7-03)

 

ARTICLE 230-10 (Page 192) is deleted and the following substituted:

D2300010 230; 230 Items
234      SUPERPAVE ASPHALT BASE.
(REV 11-1-02) (FA 1-14-03) (7-03)

 

PAGE 192. The following new Section is added after Section 230.

D2340000 285-7xx; 2285-7xx 
240      SAND-CLAY BASE.
(REV 10-31-01) (FA 1-3-02) (7-02)

 

ARTICLE 240-5 (Page 194) is deleted and the following substituted:

D2400000 285-7xx; 2285-7xx
250      SHELL BASE.
(REV 11-4-02) (FA 12-13-02) (7-03)

 

ARTICLE 250-11 (Page 196) is deleted and the following substituted:

D2500011 285; 2285 Items
260       SHELL STABILIZED BASE-BASIS OF PAYMENT.
(REV 11-1-02) (FA 1-14-03) (7-03)

 

ARTICLE 260-10 (Pages 197 and 198) is deleted and the following substituted:

D2600010 260-1; 2260-1;
260-2; 2260-2
280      ASPHALT BASE COURSES.
(REV 12-19-01) (FA 1-4-02) (7-02)

SECTION 280 (Page 207-209) is deleted and the following substituted:
D2800000 285-7xx; 2285-7xx 
283        RECLAIMED ASPHALT PAVEMENT BASE..
(REV 1-7-01) (FA 1-3-02) (7-02)

SECTION 283 (Pages 209-211) is deleted and the following substituted:
D2830000 285-7xx; 2285-7xx 
285        OPTIONAL BASE COURSE.
(REV 10-31-01) (FA 1-4-02) (7-02)

SECTION 285 (Pages 211-213) is deleted and the following substituted:
D2850000 285-7xx; 2285-7xx 
286        TURNOUT CONSTRUCTION-METHOD OF MEASUREMENT.
(REV 6-20-00) (FA 9-13-00) (7-01)

ARTICLE 286-5 (Page 214) is deleted and the following substituted
D2860005 286; 2286 Items 
288        CEMENT TREATED PERMEABLE BASE.
(REV 11-5-01) (FA 1-3-02) (7-02)

PAGE 215. The following new Section is added after Section 286:
D2880000 288; 2288 Items
300        PRIME AND TACK COATS FOR BASE COURSES.
(REV 1-13-03) (FA 1-15-03) (7-03)

SECTION 300 (Pages 217-221) is deleted and the following substituted:
D3000000 Jobs with Asphalt
310      BITUMINOUS SURFACE TREATMENT - METHOD OF MEASUREMENT.
(REV 11-1-02) (FA 1-14-03) (7-03)

 

SUBARTICLE 310-14 (Page 228) is expanded by the following new Subarticle: 

D3100014 300-1; 2300-1
311     SAND SEAL COAT - METHOD OF MEASUREMENT.
(REV 11-4-02) (FA 1-14-03) (7-03)

 

ARTICLE 311-6 (Page 230) is expanded by the following new Subarticle: 

D3110006 300-1; 2300-1
312     BITUMINOUS CRACK RELIEF LAYER - METHOD OF MEASUREMENT.
(REV 11-4-02) (FA 1-15-03) (7-03)

 

ARTICLE 312-14 (Page 233) is expanded by the following new Subarticle:

D3120014 300-1; 2300-1
320     HOT BITUMINOUS MIXTURES-PLANT, METHODS, AND EQUIPMENT.
(REV 12-19-01) (FA 1-4-02) (7-02)

SECTION 320 (Pages 233-241) is deleted and the following substituted:
D3200000 Jobs with Asphalt
327     MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 12-19-01) (FA 1-4-02) (7-02)

SECTION 327 (Pages 241-243) is deleted and the following substituted:
D3270000 327-70; 2327-70
330      HOT BITUMINOUS MIXTURES-GENERAL CONSTRUCTION REQUIREMENTS.
(REV 1-8-03) (FA 1-15-03) (7-03)

SECTION 330 (Pages 244-266) is deleted and the following substituted:
D3300000 Jobs with Asphalt
331      TYPE S ASPHALT CONCRETE, QUALITY ASSURANCE AND ACCEPTANCE PROCEDURES.
(REV 9-26-01) (FA 1-4-02) (7-03)

SECTION 331 (Pages 266-279) is deleted and the following substituted:
D3310000 331-2; 2331-2
332      TYPE II ASPHALTIC CONCRETE.
(REV 9-26-01) (FA 1-3-02) (7-02)

SECTION 332 (Pages 279-281) is deleted and the following substituted:
D3320000 332-2; 2332-2
333      TYPE III ASPHALTIC CONCRETE.
(REV 9-26-01) (FA 1-3-02) (7-02)

SECTION 331 (Pages 281-283) is deleted and the following substituted:
D3330000 333-2; 2333-2
334      SUPERPAVE ASPHALT CONCRETE.
(REV 12-24-02) (FA 1-15-03) (7-03)

 

SECTION 334 (Pages 283-304) is deleted and the following substituted:

D3340000 334, 2334 Items
335      SAND-ASPHALT HOT MIX.
(REV 9-27-01) (FA 1-3-02) (7-02)

SECTION 335 (Pages 304-306) is deleted and the following substituted:
D3350000 335-2; 2335-2
336      ASPHALT RUBBER BINDER.
(REV 9-27-01) (FA 1-4-02) (7-02)

SECTION 336 (Pages 306-308) is deleted and the following substituted:
D3360000 334, 2334; 337, 2337; 341, 2341 Items
337      ASPHALT CONCRETE FRICTION COURSES.
(REV 11-6-02) (FA 1-14-03) (7-03)

 

SECTION 337 (Pages 309-317) is deleted and the following substituted:

D3370000 337-7; 2337-7
339      MISCELLANEOUS ASPHALT PAVEMENT.
(REV 11-4-02) (FA 1-14-03) (7-03)

SECTION 339 (Pages 317 and 318) is deleted and the following substituted:
D3390000 339-1, 2339-1
341      ASPHALT RUBBER MEMBRANE INTERLAYER.
(REV 11-5-02) (FA 1-14-03) (7-03)

SECTION 341 (Pages 319-321) is deleted and the following substituted:
D3410000 341, 2341 Items
346      PORTLAND CEMENT CONCRETE.
(REV 1-9-03) (FA 2-5-03) (7-03)

 

SECTION 346 (Pages 321-346) is deleted and the following substituted:

D3460000 Jobs with Concrete
347      PORTLAND CEMENT CONCRETE-CLASS I (NONSTRUCTURAL).
(REV 5-21-01) (FA 6-20-01) (1-02)

SECTION 347 (Pages 346-349) is deleted and the following substituted:
D3470000 Jobs with Nonstructural Concrete
352      GRINDING CONCRETE PAVEMENT.
(REV 3-28-02) (FA 4-9-02) (1-03)

SECTION 339 (Pages 369-373) is deleted and the following substituted:
D3520000 Jobs with Concrete Pavement
353      CONCRETE PAVEMENT SLAB REPLACEMENT.
(REV 3-28-02) (FA 4-9-02) (7-03)

PAGE 373. The following Section is added after 352:
D3530000 353-70; 2353-70
400      CONCRETE STRUCTURES.
(REV 1-15-03) (FA 1-21-03) (7-03)

SECTION 400 (Pages 375-412) is deleted and the following substituted:
D4000000 Jobs with Concrete Structures 
407     THREE-SIDED PRECAST CULVERT.
(REV 5-9-02) (FA 7-11-02) (1-03)

ARTICLE 407-1 (Page 413) is deleted and the following substituted:
D4070002 When called for in the plans
410     PRECAST CONCRETE BOX CULVERT.
(REV 6-24-02) (FA 7-11-02) (1-04)

ARTICLE 410-1 (Page 415) is deleted and the following substituted:
D4100002 When called for in the plans 
413     SEALING CONCRETE STRUCTURE SURFACES.
(REV 8-23-01) (FA 12-20-01) (7-02)

SECTION 413 (Pages 420-423) is deleted and the following substituted:
D4130000 400-149, 2400-149; 400-154, 2400-154
415     REINFORCING STEEL.
(REV 4-2-01) (FA 5-11-01) (1-02)

SECTION 415 (Pages 423-429) is deleted and the following substituted:
D4150000 Jobs with Reinforcing Steel 
416     INSTALLING ADHESIVE-BONDING ANCHORS AND DOWELS FOR STRUCTURAL APPLICATIONS.
(REV 5-1-02) (FA 7-19-02) (1-03)

SECTION 416 (Pages 429 and 430) is deleted and the following substituted:
D4160000 All Jobs 
425     INLETS, MANHOLES, AND JUNCTION BOXES.
(REV 5-9-02) (FA 7-11-02) (7-03)

ARTICLE 425-3 (Page 431) is deleted and the following substituted:
D4250003 425; 2425 Items 
430     PIPE CULVERTS AND STORM SEWERS.
(REV 1-9-03) (FA 1-28-03) (7-03)

SECTION 430 (Pages 434-446) is deleted and the following substituted:
D4300000 430; 2430 Items
431     PIPE LINER.
(REV 9-21-00) (FA 1-19-01) (7-01)

SECTION 431 (Pages 446-448) is deleted and the following substituted:
D4310000 431; 2431 Items
440     UNDERDRAINS.
(REV 5-9-02) (FA 7-11-02) (1-03)

SECTION 440 (Pages 449-451) is deleted and the following substituted:
D4400000 440; 2440 Items
443     FRENCH DRAINS.
(REV 9-20-02) (FA 9-27-02) (7-03)

SUBARTICLE 443-2.1 (1) (Pages 457 and 458) is deleted and the following substituted:
D4430002 443; 2443 Items
449      PRECAST CONCRETE DRAINAGE PRODUCTS.
(REV 6-24-02) (FA 8-8-02) (1-03)

PAGE 462. The following new Section is added after Section 446:
D4490000 All Jobs
450      PRECAST PRESTRESSED CONCRETE CONSTRUCTION.
(REV 7-8-02) (FA 7-22-02) (1-03)

SECTION 450 (Pages 462-508) is deleted and the following substituted:
D4500000 Prestressed Jobs 
453      EPOXY JOINTING OF PRECAST SEGMENTS.
(REV 1-28-03) (FA 2-6-03) (7-03)

 

PAGE 524. The following new Section is added after Section 451. 

D4530000 Jobs with Concrete
455     STRUCTURES FOUNDATIONS.
(REV 5-10-02) (FA 7-11-02) (1-03)

SECTION 455 (Pages 525-598) is deleted and the following substituted:
D4550000 Structure Foundations Jobs
460     STRUCTURAL STEEL AND MISCELLANEOUS METALS.
(REV 5-7-01) (FA 10-23-01) (7-03)

SUBARTICLE 460-2.1 (Page 600) is deleted and the following substituted:
D4600000 Jobs with Structural Steel 
461     MULTIROTATIONAL BEARINGS.
(REV 11-19-02) (FA 12-13-02) (7-03)

 

PAGE 620. The following new Section is added after Section 460: 

D4610000 461-113, 2461-113;
461-114, 2461-114
465     MOVABLE BRIDGES.
(REV 8-2-02) (FA 9-3-02) (7-03)

 

SECTION 465 (Pages 620-623) is deleted and the following substituted: 

D4650000 Movable Bridge Jobs
502     SHEAR CONNECTORS.
(REV 4-3-01) (FA 4-27-01) (7-01)

ARTICLE 502-1 (Page 627) is deleted and the following substituted:
D5020000 Jobs with Structural Steel
508     ELECTRICAL CONSTRUCTION FOR MOVABLE BRIDGES.
(REV 8-2-02) (FA 9-3-02) (7-03)

 

SECTION 508 (Pages 634-641) is deleted and the following substituted:

D5080000 Movable Bridge Jobs
512     CONTROL HOUSE.
(REV 7-25-02) (FA 9-3-02) (7-03)

 

SECTION 512 (Pages 642 and 643) is deleted and the following substituted:

D5120000 512; 2512 Items
521     CONCRETE BARRIERS, TRAFFIC RAILING BARRIERS AND PARAPETS.
(REV 7-27-00) (FA 8-1-00) (1-01)

SECTION 521 (Pages 650-653) is deleted and the following substituted:
D5210000 521; 2521 Items 
522     CONCRETE SIDEWALK-METHOD OF MEASUREMENT.
(REV 5-24-00) (FA 9-26-00) (7-01)

ARTICLE 522-9 (Page 654) is deleted and the following substituted: 
D5220009 522; 2522 Items 
524     CONCRETE DITCH AND SLOPE.
(REV 6-18-02) (FA 7-17-02) (1-03)

SECTION 524 (Pages 655 and 656) is deleted and the following substituted:
D5240000 524; 2524 Items 
525     ASPHALTIC CONCRETE CURB-MATERIALS.
(REV 6-11-02) (FA 7-17-02) (1-03)

ARTICLE 525-2 (Page 656) is deleted and the following substituted: 
D5250002 525-1; 2525-1 
526     ARCHITECTURAL PAVERS.
(REV 11-18-02) (FA 1-28-03) (7-03)

Page 657. The following new Section is added after Section 525: 
D5260000 526-1; 2526-1 
530      RIPRAP.
(REV 10-15-01) (FA 1-3-02) (7-03)

SECTION 530 (Pages 657-662) is deleted and the following substituted:
D5300000 530; 2530 Items 
534      NOISE BARRIER WALL - MATERIALS.
(REV 8-21-02) (FA 12-13-02) (7-03)

 

SUBARTICLE 534-2 (Pages 662 and 663) is deleted and the following substituted:

D5340002 534-72; 2534-72
536     GUARDRAIL-CERTIFICATION.
(REV 5-2-01) (FA 6-14-01) (7-02)

ARTICLE 536-2 (Pages 666-668) is expanded by the following: 
D5360002 536; 2536 Items 
548      RETAINING WALL SYSTEMS.
(REV 1-24-03) (FA 1-31-03) (7-03)

 

SECTION 548 (Pages 674-681) is deleted and the following substituted: 

D5480000 Jobs with Retaining Wall Systems
550     FENCING-CERTIFICATION.
(REV 5-2-01) (FA 6-14-01) (7-02)

ARTICLE 550-3 (Page 682) is expanded by the following: 
D5500003 550; 2550 Items 
555      DIRECTIONAL BORE.
(REV 5-24-02) (FA 7-24-02) (1-03)

Page 686. The following new Section is added after Section 550: 
D5550000 555-1; 2555-1 
556      JACK AND BORE.
(REV 6-14-02) (FA 7-24-02) (1-03)

Page 686. The following new Section is added after Section 550: 
D5560000 556-1; 2556-1 
557      VIBRATORY PLOWING.
(REV 6-14-02) (FA 7-24-02) (1-03)

Page 686. The following new Section is added after Section 550: 
D5570000 557-1; 2557-1 
563      ANTI-GRAFFITI COATING  SYSTEM.
(REV 8-15-00) (FA 9-7-00) (7-01)

SECTION 563 (Pages 697-699) is deleted and the following substituted: 
D5630000 563; 2563 Items 
575     SODDING-WATERING.
(REV 3-10-00) (FA 4-5-00) (1-01)

SUBARTICLE 575-3.3 (Pages 703 and 704) is deleted and the following substituted:
D5750033 Sodding Jobs 
580     LANDSCAPING INSTALLATION-PLANTS.
(REV 12-6-99) (FA 12-23-99) (7-00)

SUBARTICLE 580-2.1.2 (Pages 707 and 708) is deleted and the following substituted:
D5800002 Landscaping Jobs
603     SUBMITTAL DATA REQUIREMENTS.
(REV 1-8-02) (FA 2-6-02) (1-03)

ARTICLE 603-7 (Page 715). The first paragraph is deleted and the following substituted:
D6030007 Jobs with Signal
611     ACCEPTANCE OF SIGNAL INSTALLATIONS.
(REV 4-5-02) (FA 5-22-02) (1-03)

ARTICLE 611-2 (Page 717) is expanded as follows:
D6110002 Jobs with Signal 
620     SIGNAL INSTALLATION GROUNDING.
(REV 7-12-01) (FA 1-3-02) (7-02)

SECTION 620 (Pages 721-724) is deleted and the following substituted:
D6200000 All Jobs 
630     CONDUIT-INSTALLATION REQUIREMENTS.
(REV 10-18-02) (FA 1-14-03) (7-03)

 

SUBARTICLE 630-3.1 (Pages 724 and 725) is expanded by the following: 

D6300311 630; 2630 Items 
632      SIGNAL AND INTERCONNECT CABLE.
(REV 7-25-00) (FA 8-3-00) (7-02)

SECTION 632 (Pages 728-730) is deleted and the following substituted:
D6320000 632; 2632 Items 
641      PRESTRESSED CONCRETE POLES.
(REV 3-7-00) (FA 5-8-00) (1-01)

SECTION 641 (Pages 739 and-740) is deleted and the following substituted:
D6410000 641; 2641 Items 
649      STEEL STRAIN POLES, STEEL MAST ARM AND MONOTUBE ASSEMBLIES.
(REV 1-7-02) (FA 1-10-02) (7-02)

PAGE 740. The following new Section is added after Section 641.
D6490000 649; 2649 Items 
650      VEHICULAR SIGNAL ASSEMBLIES-METHOD OF MEASUREMENT.
(REV 10-3-00) (FA 1-10-01) (7-01)

ARTICLE 650-4 (Page 742) is expanded as follows:
D6500004 650-5; 2650-5 
660       INDUCTIVE LOOP DETECTORS.
(REV 7-12-01) (FA 12-19-01) (7-03)

ARTICLE 660-6.2 (Pages 746 and 747) is deleted and the following substituted:
D6600062 660; 2660 Items 
690      REMOVAL OF EXISTING TRAFFIC SIGNAL EQUIPMENT.
(REV 5-3-01) (FA 5-15-01) (1-02)

SECTION 690 (Pages 754-757) is deleted and the following substituted:
D6900000 690; 2690 Items 
699       INTERNALLY ILLUMINATED SIGNS.
(REV 6-23-01) (FA 8-23-01) (7-02)

PAGE 757. The following new Section is added after Section 690.
D6990000 699-1; 2699-1
700    HIGHWAY SIGNING-SIGN PANELS.
(REV 7-26-02) (FA 7-30-02) (7-03)

SUBARTICLE 700-2.2 (Page 758) The fourth paragraph is deleted and the following substituted:
D7000022 All Jobs
701       RAISED RIB SHOULDER WARNING DEVICES.
(REV 8-27-01) (FA 11-9-01) (7-02)

SUBARTICLE 701-4.1 (Pages 769 and 770) is expanded by  the following:
D7010041 701; 2701 Items
702    INVERTED PROFILE, WET WEATHER TRAFFIC STRIPES.
(REV 8-27-01) (FA 10-25-01) (7-03)

PAGE 772. The following new Section is added after Section 701.
D7020000 702; 2702 Items
704    CERAMIC PAVEMENT MARKERS.
(REV 12-17-93) (FA 8-4-98) (7-00)

PAGE 772. The following new Section is added after Section 701. 
D7040000 704; 2704 Items
705     HIGHWAY DELINEATORS.
(REV 10-21-02) (FA 12-4-02) (7-03)

 

SECTION 705 (Pages 772 and 773) is deleted and the following substituted:

D7050000 705; 2705 Items
706     RAISED RETRO-REFLECTIVE PAVEMENT MARKERS AND BITUMINOUS ADHESIVE.
(REV 11-14-02) (FA 12-10-02) (7-03)

 

SECTION 706 (Pages 773-775) is deleted and the following substituted:

D7060000 706-3; 2706-3
709     TRAFFIC STRIPES AND MARKINGS-TWO REACTIVE COMPONENTS.
(REV 8-27-01) (FA 12-19-01) (7-02)

SUBARTICLE 709-4.1(Page 776) is expanded by the following:
D7090041 709, 2709 Items 
711     THERMOPLASTIC TRAFFIC STRIPES AND MARKINGS.
(REV 8-27-01) (FA 10-25-01) (7-02)

SUBARTICLE 711-4.1(Page 785) is expanded by the following:
D7110041 711; 2711 Items 
713     PREFORMED PAVEMENT STRIPES AND MARKINGS.
(REV 9-17-01) (FA 12-19-01) (7-02)

SUBARTICLE 713-4.1(Page 789) is expanded by the following:
D7130041 When called for 
714     MOTORIST AID CALL BOX RELOCATION.
(REV 11-30-00) (FA 2-2-01) (7-01)

PAGE 791. The following new Section is added after Section 713:
D7140000 714-1, 2714-1; 400-2, 2400-2 (requires plan details)
715     HIGHWAY LIGHTING SYSTEM.
(REV 11-14-01) (FA 12-19-01) (7-02)

SECTION 715 (Pages 791-797) is deleted and the following substituted:
D7150000 Highway Lighting Projects
901     COARSE AGGREGATE.
(REV 1-10-02) (FA 1-10-02) (7-03)

SECTION 901 (Pages 798-803) is deleted and the following substituted:
D9010000 All Jobs
902      FINE AGGREGATE.
(REV 8-23-01) (FA 1-10-02) (7-02)

SECTION 902 (Pages 804-807) is deleted and the following substituted:
D9020000 All Jobs
916      BITUMINOUS MATERIALS.
(REV 6-18-02) (FA 7-12-02) (1-03)

SECTION 916 (Pages 815-825) is deleted and the following substituted:
D9160000 Asphalt Jobs
919      GROUND TIRE RUBBER FOR USE IN ASPHALT RUBBER BINDER.
(REV 10-10-01) (FA 1-10-02) (7-02)

SECTION 919 (Pages 826-828) is deleted and the following substituted:
D9190000 Asphalt Jobs (use with pay items 337, 2337; 341 and 2341)
921       PORTLAND CEMENT AND BLENDED CEMENT.
(REV 1-9-02) (FA 1-10-02) (7-02)

SECTION 921 (Pages 829-832) is deleted and the following substituted:
D9210000 Jobs with Concrete
923       WATER FOR CONCRETE.
(REV 10-29-01) (FA 12-20-02) (1-03)

SECTION 923 (Page 832) is deleted and the following substituted:
D9230000 Jobs with Concrete
924       ADMIXTURES WITH CONCRETE.
(REV 7-19-02) (FA 9-30-02) (7-03)

SECTION 924 (Pages 833-835) is deleted and the following substituted:
D9240000 Jobs with Admixtures for Concrete
925       CURING MATERIALS FOR CONCRETE.
(REV 9-28-01) (FA 1-10-02) (7-02)

SECTION 925 (Pages 836 and 837) is deleted and the following substituted:
D9250000 Jobs with Concrete
926      EPOXY COMPOUNDS.
(REV 10-7-02) (FA 12-20-02) (7-03)

 

SECTION 926 (Pages 837-844) is deleted and the following substituted:

D9260000 Jobs with Concrete
929      POZZOLANS AND SLAG.
(REV 9-28-01) (FA 2-5-02) (7-03)

SECTION 929 (Pages 845-847) is deleted and the following substituted:
D9290000 Jobs with Concrete
930      MATERIALS FOR CONCRETE REPAIR.
(REV 11-30-01) (FA 1-10-02) (7-02)

SECTION 930 (Pages 847-852) is deleted and the following substituted:
D9300000 Jobs with Concrete
931      METAL ACCESSORY MATERIALS FOR CONCRETE PAVEMENT AND CONCRETE STRUCTURES-CERTIFICATION.
(REV 11-27-00) (FA 3-20-01) (1-02)

SUBARTICLE 931-2.1 (Pages 853 and 854) is expanded as follows:
D9310002 All Jobs
932      NON-METAL ACCESSORY MATERIALS FOR CONCRETE PAVEMENT AND CONCRETE STRUCTURES.
(REV 9-11-02) (FA 9-11-02) (7-03)

SECTION 932 (Pages 855-866) is deleted and the following substituted:
D9320000 All Jobs 
933     ACCESSORY MATERIALS FOR PRESTRESSED CONCRETE.
(REV 8-5-02) (FA 10-3-02) (7-03)

 

SECTION 933 (Pages 866-869) is deleted and the following substituted:

D9330000 All Jobs
934     NON-SHRINK GROUT.
(REV 12-20-01) (FA 1-3-02) (7-02)

SECTION 934 (Pages 869 and 870) is deleted and the following substituted:
D9340000 When non-shrink grout is called for 
935     PACKAGED, DRY, THERMOSETTING POLYMER CONCRETE MATERIAL FOR CONCRETE REPAIR.
(REV 1-7-03) (FA 2-5-03) (7-03)

 

SECTION 935 (Pages 870-872) is deleted.

D9350000 Jobs with Concrete
937     ADHESIVE BONDING MATERIAL SYSTEMS FOR STRUCTURAL APPLICATIONS.
(REV 4-30-02) (FA 7-25-02) (1-03)

SECTION 937 (Pages 873-875) is deleted and the following substituted:
D9370000 All Jobs 
938     POST-TENSIONING GROUT.
(REV 1-9-03) (FA 1-28-03) (7-03)

PAGE 875. The following new Section is added after Section 937.
D9380000 Post-Tensioning Jobs and Jobs with cylinder piles
941     CONCRETE PIPE.
(REV 5-9-02) (FA 7-12-02) (1-03)

SECTION 941 (Pages 844-846) is deleted.
D9410000 430; 2430 Items 
943     CORRUGATED STEEL PIPE AND PIPE ARCH (INCLUDING UNDERDRAIN).
(REV 11-21-00) (FA 1-17-01) (7-01)

ARTICLE 943-1 (Page 882) is deleted and the following substituted:
D9430001 430; 2430 Items 
945      ADHESIVE BONDING MATERIAL SYSTEMS FOR STRUCTURAL APPLICATIONS.
(REV 11-21-00) (FA 1-10-01) (7-01)

ARTICLE 945-1 (Page 887) The first paragraph is deleted and the following substituted:
D9450001 430; 2430 Items 
948      MISCELLANEOUS TYPE OF PIPE.
(REV 4-23-01) (FA 6-14-01) (7-02)

SUBARTICLE 948-1.7 (Page 892) is deleted and the following substituted: 
D9480001 430; 2430 Items 
948      PIPE LINER MATERIALS.
(REV 9-21-00) (FA 1-17-01) (7-01)

SECTION 948 (Pages 891-893) is expanded by the following:
D9480004 431; 2431 Items 
951      INSPECTION OF TIMBER PRODUCTS.
(REV 11-13-01) (FA 1-3-02) (7-02)

ARTICLE 951-1 (Pages 894) is deleted and the following substituted:
D9510001 All Jobs 
955     TIMBER TREATMENT (INCLUDING TREATING MATERIALS).
(REV 1-11-02) (FA 2-21-02) (1-03)

SECTION 955 (Pages 898-900) is deleted and the following substituted:
D9550000 All Jobs 
967     RAIL ELEMENTS FOR GUARDRAIL.
(REV 9-16-02) (FA 12-12-02) (7-03)

 

ARTICLE 967-1 (Page 910) is deleted and the following substituted: 

D9670001 536; 2536 Items
970      MATERIALS FOR RAISED RETRO-REFLECTIVE PAVEMENT MARKERS AND BITUMINOUS ADHESIVE.
(REV 11-14-02) (FA 12-10-02) (7-03)

SECTION 970 (Pages 911 and 912) is deleted and the following substituted:

D9700000 Jobs with Reflective Pavement Markers 
971      COATINGS AND TRAFFIC MARKING MATERIALS-CERTIFICATION.
(REV 12-27-00) (FA 8-3-01) (7-02)

SUBARTICLE 971-1.4 (Page 913) is deleted and the following substituted:
D9710015 All Jobs 
971      COATINGS AND TRAFFIC MARKING MATERIALS.
(REV 5-4-00) (FA 5-26-00) (7-01)

SECTION 971 (Pages 913-945) is expanded by the following:
D9710022 All Jobs 
975      ELASTOMERIC COATING SYSTEM.
(REV 10-8-02) (FA 2-5-03) (7-03)

 

PAGE 948. The following new Section is added after Section 972: 

D9750000 All Post Tensioning Jobs
982       COMMERCIAL FERTILIZER-CERTIFICATION.
(REV 11-27-00) (FA 3-28-01) (1-02)

SECTION 982 (Pages 951) is expanded as  follows:
D9820002 All Jobs 
985       GEOTEXTILE FABRICS.
(REV 10-20-99) (FA 12-21-99) (7-02)

SECTION 985 (Pages 951 and 952) is deleted and the following substituted:
D9850000 All Jobs 
986       CALCIUM CHLORIDE FOR DUST CONTROL-CERTIFICATION.
(REV 1-8-01) (FA 3-7-01) (1-02)

SECTION 986 (Pages 952 and 953) is expanded by the following:
D9860003 All Jobs 
987       FINISH SOIL LAYER MATERIALS.
(REV 5-22-02) (FA7-12-02) (1-03)

SECTION 987 (Page 953) is deleted and the following substituted:
D9870000 Grassing Jobs 
990       TEMPORARY TRAFFIC CONTROL DEVICES MATERIALS.
(REV 6-17-02) (FA 8-20-02) (1-03)

SECTION 990 (Page 954). The following Section is added after Section 987: 
D9900000 All Jobs 
992       HIGHWAY LIGHTING MATERIALS-CERTIFICATION.
(REV 5-3-02) (FA 5-16-02) (1-03)

ARTICLE 992-4 (Page 955) is expanded by the following Subarticles:
D9920041 All Jobs 
992       POLE CABLE DISTRIBUTION SYSTEM-WALL MOUNTED LIGHTING.
(REV 3-14-00) (FA 5-15-00) (1-01)

SUBARTICLE 992-12 (Pages 957-960) is expanded by the following new Subarticle:
D9920012 Lighting Jobs 
993      HIGHWAY DELINEATORS.
(REV 10-21-02) (FA 12-4-02) (7-03)

 

SECTION 993 (Pages 961 and 962) is deleted and the following substituted:

D9930000 705; 2705 Items 
994       RETROREFLECTIVE AND NONREFLECTIVE SIGN SHEETING.
(REV 7-6-00) (FA 7-25-00) (1-01)

SECTION 994 (Pages 964-973) is deleted and the following substituted:
D9940000 All Jobs 
995       DEMOUNTABLE SIGN FACE MATERIALS-CERTIFICATION.
(REV 11-27-00) (FA 3-7-01) (1-02)

ARTICLE 995-3 (Page 976) is deleted and the following substituted:
D9950003 All Jobs 
996       PORCELAIN ENAMEL LAMINATED ALUMINUM SIGN PANELS-CERTIFICATION.
(REV 1-8-01) (FA 3-28-01) (1-02)

SECTION 996 (Pages 976-980) is expanded by the following:
D9960006 All Jobs 
APPENDICES DAPENDIC  
TECHNICAL SPECIAL PROVISIONS.
The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package.

Insert # ________

TSPs Jobs with TSPs
Insert File names of the WORD Tsp’s for the Macro to bring the files in automatically. For more than one file, TAB to add more rows File Name here Individual TSPs