Inclusion into the Request for Proposal (RFP)
January - June 2007
The Design-Build Specifications is the boiler-plate Master Document) to be used in the Request for Proposal (RFP) for Design-Build projects.
The files below contain optional text which may be incorporated (copy and paste) into the Design-Build (Master Document) for inclusion into the RFP, to create specific Contract language.
| File | Title | Usage Notes |
|---|---|---|
| When other Contractors are working in the area | ||
| SP000044 | Intent of Contract | When other Contractors are working in the vicinity |
| To Change Award and Execution Time | ||
| SP0030200 | Award and Execution of Contract | When necessary to change standard "Award and Execution" |
| Structures Over 1500 Feet in Length (over water) | ||
| SP0050901 | Inspection | Long bridge jobs (1500 feet or longer); modify to suit |
| Toll Facility (TurnPike Only) | ||
| SP0070200 | Permits and Licenses (No free passes will be issued to the Contractor for use on the Toll Facility) | Use when requested. |
| Building(s) | ||
| SP007201B | Permits Procured by the Contractor | Jobs with buildings |
| Use of Explosives | ||
| SP0070900 | Use of Explosives | When explosives are prohibited |
| Special Start Time | ||
| SP008030A | Prosecution of Work - Flexible Start Time | When called for |
| SP0080303B | Beginning Work (Number of days after Contract execution to issue NTP) | Only when called for by the District Construction Engineer |
| SP0080303C | Beginning Work (Specific Date) | Only when called for by the District Construction Engineer |
| Partnering | ||
| SP0080306 | Prosecution of Work - Partnering | 999-16 |
| Disputes Review Board | ||
| SP0080307RDRB | Regional Disputes Review Board | Jobs without Pay Item No. 999-20 |
| SP0080307SDRB | Statewide Disputes Review Board | Jobs with Asphalt Pavement, Concrete Pavement, Performance Turf or Landscape Installation |
| Jobs with Lighting | ||
| SP0080409 | Hazardous or Toxic Waste - Mercury - Containing Devices and Lamps | Jobs with lighting |
| Damage Recovery | ||
| SP0081300 | Damage Recovery | Use when requested by proper authority. (Do not use with Lane Rental.) |
| Alternative Bidding | ||
| SP0081300A | Prosecution and Progress | All Jobs with Alternative Bidding. (Use with proper authority.) |
| Bonus | ||
| Date Specific | ||
| SP0081300B | "Bonus" Payment and Waiver of Contractor Claims | Bonus (Date Specific) (Use with proper authority) |
| Calendar Days | ||
| SP0081300BCD | "Bonus” Payment and Waiver of Contractor Claims | Bonus (Calendar Days) (Use with proper authority) |
| Milestone | ||
| SP0081300MB | "Bonus" Payment and Waiver of Contractor Claims | Milestone Bonus (Use with proper authority). Do not use with SP00813000B or SP0081300BCD. |
| Liquidated Savings | ||
| SP0081300LQS | Liquidated Savings for Early Completion | Liquated Savings. (Use with proper authority) |
| Incentive - Disincentive | ||
| SP0081300ID | Incentive - Disincentive | Incentive – Disincentive. (Use with proper authority) |
| Milestone | ||
| SP0081300MID | Incentive - Disincentive | Milestone Incentive-Disincentive. (Use with proper authority). Do not use with SP0081300ID) |