Palm Beach County Construction - March 7, 2012

More About District Four
|
 |
I-95 HOV Expansion from Donald Ross Road north to S.R. 706/ Indiantown Road
- Construction will expand the existing six-lane interstate to 10 lanes, which includes one general-purpose lane and one High Occupancy Vehicle (HOV) lane in each direction and additional auxiliary lanes. The project includes widening of the existing bridges over Donald Ross Road and the C-18 Canal; ramp improvements; sound barrier and retaining wall construction; signalization enhancements; new signing, pavement markings, lighting; and landscaping, including irrigation.
- Project start date: August 2008
- Project estimated completion: fall 2012
- Contractor: Posen Construction
I-95 HOV Expansion from south of PGA Boulevard north to Donald Ross Road
- Construction will expand the existing six-lane interstate to 10 lanes, which includes one general-purpose lane and one High Occupancy Vehicle (HOV) lane in each direction and additional auxiliary lanes. The project includes mainline ramp reconstruction and the widening of the existing bridges over PGA Boulevard and Military Trail (exit 79C). Additional enhancements include improved drainage; sound barrier and retaining wall construction; new signing, pavement markings, lighting, and landscaping.
- Project start date: August 2008
- Project estimated completion: spring 2012
-
Contractor: Community Asphalt Corporation
I-95 Intelligent Transportation System (ITS) Deployment Project
- This Design/Build ITS Deployment project will establish a permanent Intelligent Transportation System (ITS) network along I-95 through Palm Beach County and includes: installing Dynamic Message Signs on I-95 and on crossroads with entrance and exit ramps to/from I-95; and installing Highway Advisory Radio and other ITS-related equipment. The project is being done in two phases. Phase A is underway between the Broward-Palm Beach County line and PGA Boulevard. This phase is expected to be completed by January 2011. Phase B, from PGA Boulevard to the Palm Beach-Martin County Line, will start when Phase A is completed.
- Project start date: October 2008
- Project estimated completion: late 2012
- Contractor: Transcore ITS
I-95 Northbound Resurfacing Project
- This project includes milling and resurfacing of the existing roadway, and the restoration of traffic monitoring loops that will be removed during milling operations.
- Project start date: May 22, 2011
- Project estimated completion: winter 2011
- Contractor: Community Asphalt Corporation
I-95 Overhead Sign Installation - Congress Avenue to Boynton Beach Boulevard
- This project includes overhead sign panel installation along I-95, striping improvements, and sod installation.
- Project start date: Monday, Dec. 5, 2011
- Project estimated completion: summer 2012
- Contractor: Signal Group, Inc.
Glades Road / SR 808 From West of I-95 to NW 7th Avenue
- Work consists of repaving the roadway, installation of new sidewalks, widening to provide bike lanes, pedestrian and traffic railing upgrades, installation of video detection devices, signage, signalization, and landscaping.
- Project start date: April 18, 2011
- Project estimated completion: summer 2012
- Contractor: Ranger Construction South
State Road 802 / Lake Worth Road Improvements, east of Congress Ave.
- Work includes milling and resurfacing the roadway, bridge rehabilitation and railing upgrades, ADA and safety improvements, pedestrian signal upgrades, and irrigation installation.
- Project start date: October 24, 2011
- Project estimated completion: Early summer 2012
- Contractor: Weekley Asphalt Paving
SR 802 / Lake Worth Road
- Milling and resurfacing, guardrail installation, video detection and signalization upgrades, and drainage, landscaping and irrigation improvements.
- Project start date: July 5, 2011
- Project estimated completion: fall 2011
- Contractor: Weekly Asphalt Paving, Inc.
Southern Boulevard / S.R. 80 from Parker Avenue to Washington Road
- Work consists of milling and resurfacing Southern Boulevard, installation of new sidewalk, bridge joint replacement, crosswalk, sidewalk, and ramp upgrades to meet ADA standards, minor drainage improvements, video detection installation, and signage replacement.
- Project start date: January 3, 2012
- Project estimated completion: summer 2012
- Contractor: Community Asphalt Corporation
Southern Boulevard / Lang Road Drainage Improvements
- Work consists of milling and resurfacing Lang Road from Southern Boulevard to Shannondale Road, installation of new drainage structures and storm pipes, and re-grading the existing retention pond along Southern Boulevard, just east of Lang Road, for conversion to a wet detention pond.
- Project start date: September 6, 2011
- Project estimated completion: Early winter 2012
- Contractor: CMA Corporation
Flagler Memorial Bridge Replacement Project
- The project includes replacing the existing Flagler Memorial Bridge with a new bascule (span) bridge connecting the Town of Palm Beach and the City of West Palm Beach, over Lake Worth Lagoon and the Intracoastal Waterway. The Flagler Drive overpass will be replaced with an “at-grade” intersection. New lighting, pedestrian features, traffic signals, drainage, and landscaping are also included.
- Project start date: January 2012
- Project estimated completion: spring 2012
- Project estimated completion: winter 2014
- Contractor: PCL Civil Constructors, Inc.
SR 804 / Boynton Beach Boulevard from east of Hagen Ranch Road to west of Jog Road
- Work consisted of repaving and restriping the road,video detection upgrades to existing signals, pedestrian signal upgrades and ADA improvements, and landscaping and irrigation.
- Project start date: June 20, 2010
- Project estimated completion: October 20, 2011
- Contractor: Weekly Asphalt Paving, Inc.
SR 850 Northlake Boulevard / SR 811 Alternate A1A
- Work consists of repaving and restriping the roadway, minor drainage, minor bridge rehab, landscaping and irrigation, and signalization, signing, and pavement markings.
- Project start date: March 7, 2011
- Project estimated completion: Early spring 2012
- Contractor: Ranger Construction Industries
A1A Little Lake Worth Bridge Replacement
- Work includes replacing the existing low-level fixed bridge with a new two-lane fixed bridge in the same location. The new bridge will provide four additional feet of clearance (for a total of 12 feet) to meet current FDOT standards, and minimize future damage to the bridge deck from salt water.
- Project start date: January 3, 2012
- Project estimated completion: winter 2012
- Contractor: The Murphy Construction Company
SR 5 / US 1 Resurfacing
- Work consists of repaving and restriping the roadway, drainage replacement, landscaping and irrigation, and signalization, signage, and pavement markings.
- Project start date: Early August 2011
- Project estimated completion: spring 2013
- Contractor: Community Asphalt Corporation
SR 5 / US 1 Low-level Bridge Replacement, Design-Build
- Replacement of four (4) low-level bridges on US-1 in Jupiter with 12’ vertical clearance.
- Project start date: June 16, 2011
- Project estimated completion: fall 2012
- Contractor: Johnson Brothers
SR 809 / Military Trail Resurfacing
- Work consists of repaving and restriping the roadway, landscaping and irrigation, and signalization, signage, and pavement markings.
- Project start date: July 18, 2011
- Project estimated completion: spring 2012
- Contractor: Community Asphalt Corporation
SR 710 / Beeline Highway
- This project includes milling and resurfacing the roadway, drainage, and shoulder work.
- Project start date: September 2011
- Project estimated completion: spring 2012
- Contractor: Ranger Construction Industries
SR 80 / Guardrail Installation
- Work includes the installation of 18 miles of guardrail for canal protection alongside State Road 80.
- Project start date: November 15, 2010
- Project estimated completion: June 27, 2011
- Contractor: Design-Build Engineers & Contractors, Corp.
SR 80 / SR 880, SR 717, Belle Glade
- Work includes milling and resurfacing the roadway, ADA curb and ramp replacement, drainage improvements, pedestrian improvements and railing installation, and guardrail and landscaping installation.
- Project start date: October 17, 2011
- Project estimated completion: summer 2012
- Contractor: Weekly Asphalt Paving, Inc.
SR 25 / US 27 Resurfacing Project
- Work includes milling and resurfacing State Road 25 (US 27) from the Broward/Palm Beach County line to Mile Post 5.892, signage, and pavement markings.
- Project start date: January 31, 2012
- Project estimated completion: fall 2012
- Contractor: Asphalt Group, Inc.
Little Blue Heron Bridge
- Work included removing the existing low-level, fixed bridge and replacing it with a new four-lane fixed bridge in the same location. This tidal relief bridge spans the Lake Worth Lagoon connecting A1A from Phil Foster Park to Singer Island.
- Project start date: December 14, 2009
- Project estimated completion: September 2011
- Contractor: The Murphy Construction Company
Little Lake Worth Bridge
- This bridge replacement project includes removing the existing low-level fixed bridge with a new two-lane fixed bridge in the same location. The new bridge will provide four additional feet of clearance (for a total of 12 feet) to meet current FDOT standards and minimize future damage to the bridge deck caused by salt water.
- Project start date:
- Project estimated completion:
- Contractor: The Murphy Construction Company
|