Santa Rosa County Construction

Citizens watching a shuttle launch from the Max Brewer Bridge.

U.S. 90

 

Bridge replacement over White River and Bass Hole Cove

 

Project start date: July 2012

 

Estimated completion: summer 2015

 

Contractor: Scott Bridge Company

U.S. 90

 

From east of County Road 89 ( Ward Basin Road 0 to east of State Road 87)

 

Project start date: February 2012

 

Estimated completion: fall 2012

 

Contractor: Roads, Inc. of NWF

State Road 89

 

From County Road 178 to Jay City Limits

 

Project start date: May 2012

 

Estimated completion: winter 2013

 

Contractor: APAC Mid-South, Inc.

State Road 87

 

From north of Five Forks Road to Eglin AFB

 

Estimated completion:  spring 2013

 

Contractor: Anderson Columbia Co, Inc.

State Road 281(Avalon Boulevard) from I-10 to a point south of the Moors Lodge

 

Reconstructing the roadway from two to four lanes Also included in the contract will be drainage improvements, sidewalk construction, a new bridge built over Mulatto Bayou, minor side road improvements, installation of high mast lighting at I-10, new signs and pavements markings.

 

Project start date: March 2011

 

Estimated completion: winter 2013

 

Contractor: APAC Mid-South, Inc.

State Road 281(Avalon Boulevard) - from south of Moors Lodge to north of the CSX R/R

 

Reconstructing the roadway from two to four lanes, drainage improvements, sidewalk construction, a new bridge built over the CSX railroad, minor side road improvements, and new signs and pavements markings within the project limits.

 

Project start date: October 2010

 

Estimated completion: fall 2013

 

Contractor: Roads of NW FL, Inc.

State Road 281 (Avalon Boulevard) - from south of Admiral Road to State Road (S.R.) 10 (U.S. 90)

 

Improvements for segment five include: Reconstruction of S.R. 281 from a two lane rural roadway to a four-lane urban roadway. Additional improvements will include construction of storm drain improvements, a storm water pond, sidewalks, mast arm signal systems at Avalon Boulevard and Mulat/Commerce Road, emergency signal at S.R. 281 and Carroll Road, and S.R. 281 and S.R. 10 (U.S. 90). The improvements will also include signing and pavement markings and minor side road improvements.

 

Project start date: January 2010

 

Estimated completion: winter 2013

 

Contractor: Panhandle Grading & Paving, Inc.

State Road 281 (Avalon Boulevard) - from a point north of CSX R/R Bridge a point south of Commerce Road

 

Improvements under this American Recovery and Reinvestment Act (ARRA) project consist of reconstruction and widening the existing two-lane urban/rural roadway to a four-lane urban roadway including: construction of storm drain improvements, a storm water retention pond, sidewalks, a mast arm signal system at Avalon Boulevard and Cyanamid Road, signing and pavement markings, construction of a frontage road on the east side of Avalon Boulevard running from just south of Cactus Drive to just north of Admirals Drive as well as minor side road improvements.

 

Project start date: August 2009

 

Estimated completion: winter 2013

 

Contractor: Panhandle Grading & Paving, Inc.