Okaloosa County Construction - March 14, 2012

More About District Three
|
 |
State Road 85
- From Bill Lundy Road to the Walton County line
- Resurfacing
- Project start date: March 2012
- Estimated completion: fall 2012
- Contractor: Anderson Columbia, Co., Inc.
U.S. 90 - Shoal River Bridge
- Bridge Painting
- Project start date: February 2012
- Estimated completion: spring 2012
- Contractor: S & D Industrial Painting, Inc.
State Road 189 (Lewis Turner Boulevard)
- Resurfacing from Robert Boulevard to S.R. 397 ( Eglin Boulveard)
- Project start date: January 2012
- Estimated completion : fall 2012
- Contractor: Anderson Columbia Co., Inc.
State Road 85 (Eglin Parkway)
- From S.R. 30 ( U.S. 98) to north of Richbourg Avenue
- Project start date: January 2012
- Estimated completion : summer 2013
- Contractor: APAC Mid-South, Inc.
State Road 30 (U.S. 98) From Santa Rosa Sound Bridge to East Pass Bridge
- Resurfacing the roadway from the Santa Rosa Sound Bridge to the East Past Bridge, shoulder work near the East Pass Bridge, drainage improvements, guardrail replacement, sidewalk construction, signalization upgrades, safety improvements and placement of new pavement markings and signs.
- Project start date: October 2011
- Estimated completion: spring 2012
- C.W. Roberts Contracting, Inc.
State Road 30 (U.S. 98)
- Resurfacing from Santa Rosa County line to west of Josie Road. Drainage improvements, guardrail, traffic signal loop replacements, and new signs and pavement markings.
- Project start date: April 2011
- Estimated completion: spring 2012
- Contractor: Panhandle Grading & Paving, Inc.
State Road 4 and State Road 10 (U.S. 90)
- Widening and resurfacing project along State Road (S.R.) 4 and a portion of S.R. 10 /U.S. 90. Work on S.R. 4 will begin just north of 15th Street (south of S.R. 189 /Georgia Highway) and continue to S.R. 10 /U.S. 90 south. Improvements to U.S. 90 will be between S.R. 4 and the Yellow River Bridge to the east.
- Project start date: November 2011
- Estimated completion: winter 2012
- Contractor: Anderson Columbia Co.
State Road 85
- S.R. 85 at S.R. 123 Interchange project which extends from south of General Bond Boulevard to north of the Northwest Florida Regional Airport. This project is being funded through the American Recovery and Reinvestment Act (ARRA) of 2009. The new grade separated interchange will provide a flyover ramp for traffic on State Road (S.R.) 85 south heading northbound along S.R. 123. The project will also widen S.R. 85 south from four to six lanes and will reconstruct the entrance and exit to the Northwest Florida Regional Airport. Two bridges will be constructed on S.R. 85 to elevate through traffic on S.R. 85 over the airport exit. A new connector road will be added on the north side of S.R. 85, linking the current airport exit to S.R. 123 via two, single-lane ramps. The project also includes signage, pavement markings and lighting for the new ramp. Also, five stormwater retention ponds will be constructed.
- Project start date: August 2009
- Estimated completion: spring 2012
- Contractor: Anderson Columbia, Inc.
|