State Road A1A
Resurfacing from Mickler Road (County Road 203) to the beginning of the four-lane (2.4 miles) in Ponte Vedra.
Project start date: January 3, 2013
Project estimated completion: 90 days (Spring of 2013)
Contractor: Duval Asphalt Products
State Road 16
Resurfacing from Green Acres Road to San Marco Avenue (5 miles) and adding sidewalk from Toms Road to Kenton Morrison Road (3.5 miles) in St. Augustine.
Project start date: January 7, 2013
Project estimated completion: 210 days (Fall 2013)
Contractor: Hubbard Construction Company
State Road 206
Replacing the motors that operate the bridge raising mechanism and replacing the control console inside the bridge tenders house in Crescent Beach.
Project start date: January 3, 2013
Project estimated completion: 235 days (Fall 2013)
Contractor: Quinn Construction Inc.