Interstate 10
Adding lanes and reconstructing from east of Halsema Road to Lane Avenue (8.2 miles).
Project start date: January 12, 2009
Project estimated completion: 1,508 days (Spring 2013)
Contractor is Hubbard Construction Company
Interstate 10
Rehabilitating concrete pavement between Lane Avenue and Stockton Street (4 miles).
Project start date: June 1, 2009
Project estimated completion: 1,406 days (Spring 2013)
Contractor is Russell Engineering, Inc., of Ft. Lauderdale
Interstate 95
Rehabilitating concrete pavement between J.T. Butler Boulevard (State Road 202) and Atlantic Boulevard (SR 10) (6.6 miles).
Project start date: February 28, 2011
Project estimated completion: 720 days (Spring of 2013)
Contractor is Costello Industries Inc., of Newington, Conn.
Interstate 295
Construct a new Collins Road interchange and collector distributor road system connecting Collins Road and Blanding Boulevard (State Road 21).
Project start date: February 14, 2011
Project estimated completion: 998 days (Summer of 2013)
Contractor is Superior Construction Company of Jacksonville
Interstate 295
Installing ITS (Intelligent Transportation System) from Interstate 10 to Interstate 95 North (14 miles).
Project start date: July 16, 2011
Project estimated completion: 571 days (Early 2013)
Contractor is James D. Hinson Electrical Contracting Company Inc., of Jacksonville
Philips Highway (U.S. 1)
Updating signals and installing Intelligent Transportation System from State Road 9A to Wister Street (10.5 miles).
Project start date: April 8, 2011
Estimated completion: 537 days (Early 2013)
Contractor is American Lighting and Signalizations Inc.
State Road 9B
Design and construct a new four-lane limited access roadway from State Road 9A to Philips Highway (U.S. 1) (4.6 miles).
Project start date: July 27, 2011
Estimated completion: 1,102 days (Spring of 2013)
Contractor is Archer Western Contractors
Arlington Expressway (State Road 10)
Structural repairs and repainting the Mathews Bridge
Project start date: September 27, 2011
Estimated completion: 720 days (Fall 2013)
Contractor is Intech Contracting, LLC
Martin Luther King Jr. Parkway (State Road 115)
Building a new interchange at 21st Street/Talleyrand Avenue
Project start date: November 23, 2011
Estimated completion: 695 days (Late 2013)
Contractor is Archer Western Contractors
Main Street (US 17)
Resurfacing from Trout River Boulevard to Trout River Bridge and relocating roadway under the bridge.
Project start date: December 5, 2011
Estimated completion: 715 days (Late 2013)
Contractor is Superior Construction Company of Jacksonville
Hart Expressway (State Road 228)
Fender repairs to the Hart Bridge
Project start date: June 8, 2012
Estimated completion: 400 days (Summer 2013)
Contractor is Hal Jones Contractor Inc.
Interstate 10
Reconstructing and relocating interchange at Marietta (Exit 355)
Project start date: August 28, 2012
Estimated completion: 615 days (Fall 2014)
Contractor is Superior Construction Company
Interstate 10
Resurfacing from the Nassau County line to State Road 23 (Cecil Commerce Connector) (9 miles)
Project start date: August 1, 2012
Estimated completion: 300 days (Spring 2013)
Contractor is Anderson Columbia Company Inc.
Interstate 95
Rehabilitating concrete pavement from south of Greenland Road to just south of Butler Boulevard (State Road 202) (6.3 miles).
Project start date: September 21, 2011
Estimated completion: 1,290 days (late 2014)
Contractor is Reeves Construction
Interstate 95
Replacing the Overland Bridge which carries traffic over Hendricks, King and Montana avenues.
Project start date: August 9, 2012
Estimated completion: 1,165 days (Fall 2015)
Contractor is Archer Western Contracting Inc.
Interstate 295
Resurfacing from north of Commonwealth Avenue to the Trout River Bridge (6 miles)
Project start date: September 11, 2012
Estimated completion: 235 days (Spring 2013)
Contractor is Duval Asphalt Products
Philips Highway (US 1)
Resurfacing from Business Park Boulevard to Baymeadows Road (State Road 152) (5.2 miles)
Project start date: July 16, 2012
Estimated completion: 275 days (Spring 2013)
Contractor is Hubbard Construction Company
US 301
Adding lanes from north of Baldwin at a point where the future Baldwin Bypass will intersect and continues to the Nassau County line (3 miles)
Project start date: August 18, 2011
Estimated completion: 1,214 days (Spring 2015)
Contractor is Anderson Columbia Company Inc.
Interstate 295
Operational improvements at interchange with Commonwealth Avenue in Jacksonville.
Project start date: January 7, 2013
Estimated completion: 300 days (late 2013)
Contractor is Southern Development Corporation
Interstate 95
Replacing the series of overpasses between the Fuller Warren Bridge and north of Emerson Street (2 miles)
Project start date: January 14, 2012
Estimated completion: 1,165 days (Fall 2015)
Contractor is Archer Western Contracting Company Inc.
Atlantic Boulevard (State Road 10)
Update traffic signals from Glynlea Road to Caravan Trail (1.7 miles)
Project start date: January 3, 2013
Estimated completion: 180 days (Summer of 2013)
Contractor is James D. Hinson Electrical Contracting Company Inc.
Airport Road (State Road 102)
Installing Intelligent Transportation System (ITS) communications from Interstate 95 to Pecan Park Road
Project start date: February 1, 2013
Estimated completion: 120 days (Summer 2013)
Contractor is American Lighting and Signalizations Inc.
Jones Road
Replacing bridge over Six Mile Creek.
Project start date: January 26, 2013
Estimated completion: 220 days (Fall 2013)
Contractor is Superior Construction Company
Heckscher Drive (State Road 105)
Mechanical and electrical repairs to the Sisters Creek Bridge.
Project start date: March 1, 2013
Estimated completion: 285 days (Fall 2013)
Contractor is Superior Construction Company