Heckscher Drive (State Road 105)
- Repainting the bridge over Sisters Creek.
- Project start date: March 1, 2010
- Estimated completion: 510 days (Fall of 2011)
- Contractor is Kiewit Southern Company
Interstate 10
- Adding lanes and reconstructing from east of Halsema Road to Lane
Avenue (8.2 miles).
-
Project start date: January 12, 2009
-
Project estimated completion: 1,120 days (early 2012)
-
Contractor is Hubbard Construction Company
Interstate 10
- Rehabilitating concrete pavement between Lane Avenue and Stockton Street (4 miles).
- Project start date: June 1, 2009
- Project estimated completion: 965 days (Spring of 2012)
- Contractor is Russell Engineering, Inc., of Ft. Lauderdale
Interstate 95
- Rehabilitating concrete pavement between J.T. Butler Boulevard (State Road 202) and Atlantic Boulevard (SR 10) (6.6 miles).
- Project start date: February 28, 2011
- Project estimated completion: 720 days (Spring of 2013)
- Contractor is Costello Industries Inc., of Newington, Conn.
Interstate 295
- Construct a new Collins Road interchange and collector distributor road system connecting Collins Road and Blanding Boulevard (State Road 21).
- Project start date: February 14, 2011
- Project estimated completion: 998 days (Summer of 2013)
- Contractor is Superior Construction Company of Jacksonville
Interstate 295
- Installing ITS (Intelligent Transportation System) from Interstate 10 to Interstate 95 North (14 miles).
- Project start date: July 16, 2011
- Project estimated completion: 400 days (Fall of 2012)
- Contractor is James D. Hinson Electrical Contracting Company Inc., of Jacksonville
Ninth Street South (Jacksonville Beach)
- Resurfacing, drainage and signal improvements between Osceola Street and First Avenue South (1.7 miles)
- Project start date: January 20, 2010
- Estimated completion: 585 days (Summer of 2011)
- Contractor is A.J. Johns Inc.
Normandy Boulevard (State Road 228)
- Replacing concrete pavement from Pine Street to the beginning of the four-lane (6.5 miles) and adding westbound turn lane at McClelland Road.
- Project start date: April 14, 2011
- Estimated completion: 360 days (Spring of 2012)
- Contractor is Callaway Contracting Inc.
Normandy Boulevard (State Road 228)
- Resurfacing from the beginning of the four-lane section to the curb/urban section (7 miles).
- Project start date: August 15, 2011
- Estimated completion: 240 days (Spring of 2012)
- Contractor is Anderson Columbia Company, Inc., of Lake City
Philips Highway (U.S. 1)
- Updating signals and installing Intelligent Transportation System from State Road 9A to Wister Street (10.5 miles).
- Project start date: April 8, 2011
- Estimated completion: 360 days (Spring of 2012)
- Contractor is American Lighting and Signalizations Inc.
Roosevelt Boulevard (U.S. 17)
- Replacing concrete pavement between Woodmere Street to the end of the I-10 ramp (3.6 miles)
- Project start date: January 24, 2011
- Estimated completion: 420 days (Spring 2012)
- Contractor is Kiewit Infrastructure South Company
Roosevelt Boulevard (U.S. 17)
- Resurfacing from Yorktown Avenue to Timuquana Road (State Road 134) (2 miles).
- Project start date: August 14, 2011
- Estimated completion: 210 days (Spring of 2012)
- Contractor is Duval Asphalt Products, Inc., of Jacksonville
Southside Boulevard (State Road 115)
- Widening left turn lane at A.C. Skinner Parkway.
- Project start date: May 31, 2011
- Estimated completion:
- Contractor is Traffic Control Devices Inc., of Jacksonville
St. Johns Avenue (State Road 211)
- Bridge repair at the Ortega River Bridge.
- Project start date:
- Estimated completion: 425 days (Fall of 2011)
- Contractor is Superior Construction Company of Jacksonville
State Road 9A (Dames Point Bridge)
- Rehabilitation of the Dames Point Bridge over the St. Johns River.
- Project start date: Feb. 10, 2011
- Estimated completion: 200 days (Fall 2011)
- Contractor is Kiewett Southern Company of Tampa
State Road 9A
- Installing Intelligent Transportation System (ITS) communication system from Atlantic Boulevard to Interstate 95 North (14 miles)
- Project start date: March 28, 2011
- Estimated completion: 397 days (Spring of 2012)
- Contractor is Southeast Underground Utilities Corporation
State Road 9A
- Landscaping the interchange Butler Boulevard (State Road 202)
- July 27, 2011
- Estimated completion: 270 days (Spring of 2012)
- Contractor is Foundation Services of Central Florida Inc.
State Road 9B
- Design and construct a new four-lane limited access roadway from State Road 9A to Philips Highway (U.S. 1) (4.6 miles).
- Project start date: July 27, 2011
- Estimated completion: 881 days (Summer of 2012)
- Contractor is Archer Western Contractors
Arlington Expressway (State Road 10)
- Structural repairs and repainting the Mathews Bridge
- Project start date: September 27, 2011
- Estimated completion: 720 days (Fall 2013)
- Contractor is Intech Contracting, LLC
Southside Boulevard (State Road 115)
- Resurfacing from Cargal Street to north of Atlantic Boulevard (2.8 miles).
- Project start date: November 3, 2011
- Estimated completion: 210 days (Summer of 2012)
- Contractor is APAC-Southeast Inc., of Jacksonville
Martin Luther King Jr. Parkway (State Road 115)
- Building a new interchange at 21st Street/Talleyrand Avenue
- Project start date: November 23, 2011
- Estimated completion: 695 days (Late 2013)
- Contractor is Archer Western Contractors
103rd Street (State Road 134)
- Converting two-way left turn lanes to raised medians for safety from Danielle Terrace to Cardan Road (.5 miles)
- Project start date: November 28, 2011
- Estimated completion: 150 days (Summer 2012)
- Contractor is The Haskell Company of Jacksonville
Main Street (US 17)
- Resurfacing from Trout River Boulevard to Trout River Bridge and relocating roadway under the bridge.
- Project start date: December 5, 2011
- Estimated completion: 715 days (Late 2013)
- Contractor is Superior Construction Company of Jacksonville
State Road 9A
- Resurfacing from Monument Road to St. Johns Bluff Road (2 miles)
- Project start date: January 5, 2012
- Estimated completion: 240 days (Fall 2012)
- Contractor is Duval Asphalt Products Inc.