Columbia County Construction

Citizens watching a shuttle launch from the Max Brewer Bridge.

 

Columbia Project Information (4kb)

Adopted Five Year Citizen's Plan Report (37kb)

US 90

 

Adding two lanes from Lake City Avenue to Brown Road (1.5 miles).

 

Project start date: January 7, 2013

 

Project estimated completion: 550 days (Summer 2014)

 

Contractor is Southern Development Corporation

Southwest Bascom Norris Drive, Southwest Kuhn Road, Southwest Summers Lane, Southwest Arlington Boulevard

 

Adding sidewalk along Southwest Bascom Norris Drive from near Marvin Burnett Road by the Girls Softball Complex to US 90; along Southwest Kuhn Road from McFarlane Avenue to Bascom Norris Drive; along Arlington Boulevard from Summers to Williams lanes; and along Summers Lane from Sisters Welcome Road to Haygood Loop (on the northbound side only).

 

Project start date: March 2013

 

Project estimated completion: 280 days (Late 2013)

 

Contractor is CDM Contracting Inc.