Blanding Boulevard (State Road 21)
Installing Intelligent Transportation System from County Road 220 to Sleepy Hollow Road.
Project start date: March 4, 2012
Project estimated completion: Fall of 2012
Contractor is Traffic Control Devices Inc.
Branan Field Road (State Road 23)
Building frontage roads from Old Jennings Road to Oakleaf Plantation Parkway (4 miles).
Project start date: September 10, 2012
Project estimated completion: Fall of 2013
Contractor is Hubbard Construction Company
US 17
Resurfacing from Water Oak Lane to County Road 220 (1.7 miles).
Project start date: November 19, 2012
Project estimated completion: Spring 2013
Contractor is Hubbard Construction Company
US 17
Landscape and build perimeter wall from Holly Point Road to Elbow Road.
Project start date: May 23, 2012 (Design/Build)
Project estimated completion: 365 days (Summer 2013)
Contractor is Callaway Contracting