US 17: From County Road 634/Sweetwater Road to 7th Avenue
This project consists of widening the roadway from two to four lanes, milling and resurfacing, bridge widening and drainage improvements.
Project start date: August 2011
Estimated completion: Summer 2013
Contractor is Ajax Paving Industries of Florida, LLC
Project cost: $17.1 million
SR 66: From west of Charley Anderson Road to Charlie Creek
Work consists of widening, drainage improvements, milling and resurfacing.
Project start date: January 2013
Estimated completion: Fall 2013
Contractor is Ajax Paving Industries
Project cost: $3 million
SR 64 from Pear Street to east of Cracker Trail
This is a drainage improvement project that will include changing the elevation of the roadway in places, building gravity wall to support the new roadway, installing new curb, gutters and guardrail and paving.
Project start date: June 2013
Project estimated completion: Fall 2013
The contractor is Empower Construction, Inc.
Project cost: $776,000