Public Information Office
I-75: From the Tuckers Grade interchange (#158) to south of the North Jones Loop interchange (#161)
This project continues to six-lane the interstate. Crews will add a 12-foot travel lane and 10-foot shoulder to the inside of existing northbound and southbound I-75. This project also includes widening the bridges at Tuckers Grade and at Alligator Creek. Crews will resurface the existing ramps at the Tuckers Grade interchange and the ramps at the weigh station.
Project start date: September 2011
Project estimated completion: Spring 2013
The contractor is Ajax Paving Industries of Florida, LLC
Project cost: $12.2 million
US 17/Duncan Road: From east of Marlympia Way to west Copley Drive
The improvements include resurfacing US 17 and I-75 entrance/exit ramps at exit #164. The contractor is adding a designated bike lane in directions, widening the shoulders, and installing new drainage, guardrail and signs.
Project start: October 2012
Project estimated completion: Spring 2013
The contractor is Community Asphalt Corporation
Project cost: $2 million
SR 776: At the intersection of San Casa Drive
The improvements include intersection improvements to the traffic signal mast arms. Mast arm assemblies will include furnishing and installing galvanized steel mast arms, traffic control devices and other equipment and materials used in the construction of signalized intersections.
Project start: January 2013
Project estimated completion: Summer 2013
The contractor is Highway Safety Devices
Project cost: $154,000