Production Support
A very quick risk based "graded approach analysis" is used to
determine requirements for planning and control the the project
work effort. This analysis can maximize project control
effectiveness at the lowest cost and assist in identification
and mitigation of project risks.
INTRODUCTION
A risk-based "graded approach analysis" methodology is used to
determine requirements for planning and control of the project
work effort. This analysis will maximize project control
effectiveness at the lowest cost and assist in identification
and mitigation of project risks.
The graded approach analysis is a management tool used to:
1. Determine where to assign what PM resources;
2. Helps define scope of Project;
3. Evaluate risk elements based on risk (vs. cost of project); and,
4. Get agreement from all members of the project team.
The "Graded Approach Worksheet" should not take the project team
very long to complete, even on the most complex
project. The "Graded Approach Worksheet" is completed as part of
the Initiation Process with the total Risk Score being
documented in the Charter and Scope Statement. Completion of the
"Graded Approach Worksheet" is a fast way to quantify project
risk early in the project timeline and should not be used as a
substitute for formal risk identification, qualification,
quantification, and response planning performed during the
Planning Process.
To use this tool, you can download the word version of the
Risk Based Graded Approach Guidelines here and the Excel
Risk Based Graded Approach worksheet.
Turnpike Office has developed a similar Risk Based Graded
Approach with a different set of risk elements. The Turnpike's
Guidelines and the Excel spreadsheet files can be downloaded
here:
Turnpike's Risk Based Approach Guidelines in MS Word Format
Turnpike's Risk Based Graded Approach worksheet in MS Excel format.