The need for consistent scopes of work in 3R construction projects which focus on the original purpose of 3R work and minimize the potential for added work and increased project costs. |
Action |
|
At the March 14, 2012 Executive Workshop, a list of work items commonly included in 3R construction projects was discussed. It was agreed this list would be distributed to the Districts for review and to be used as guidance for determining the work items included in the scope of work on 3R projects. The list identifies three groups of work items common to most 3R projects:
The objective of the list of work items is to provide more consistency in 3R projects, identify items of work which may lead to scope creep, and reduce or control project costs. The District are to begin using this information to review and adjust, as necessary, the scope of work for 3R projects included in the September 2012 letting and beyond. |
|
|
|
Project Management Memorandum 12-02 - 3R project review requirements |