What is the Project Delivery Report?

The Project Delivery Report combines both the Manifest report and the Project ID report. It adds to this a Summary of Signatories and Signature Reports for each signatory in the project.

Follow these steps to view the Project Delivery Report

  1. Open up the project in PEDDS from which you will view the Project Delivery Report (instructions here).
  2. Select "Reports->Project Reports->Project Delivery Report" from the main menu.
  3. Project Delivery Report Menu Item

    Project Delivery Report Menu Item

  4. The report dialog will open displaying the Project Delivery Report for the project.
  5. Report Dialog with Project Delivery Report

    Report Dialog with Project Delivery Report

  6. From the report dialog the Project Delivery Report can be printed or saved to a PDF or Excel file.
  7. Report Dialog Menu

    Report Dialog Menu

  8. When finished, click the red "X" in the upper right of the dialog to exit.