4. Timely Completion of Project - The contractor completes the project in a timely manner.
Contractor Notification Method: Contractor notified monthly by weather letter. Contractor can appeal grade given in this category for the month within 10 days of receiving weather letter.
Guidance provided:
1. Question: Contractor is asking for the bonus points for Category 4 upfront because he is showing an early completion schedule.
Answer: Bonus points should not be awarded up front for an early completion schedule. The points, if earned, would be awarded at the end of the project. Interim grades would show 100% (or 14 points) for Category 4.