| Construction |
568+49.96 / RR |
City of PSL |
Adjust existing WM valve box |
568+49.96 |
36 RT |
PSL |
| Construction |
557+31 / LR |
Florida City Gas |
2" PE install new |
557+31 |
50-65 LT |
FCG |
| Construction |
684+60 to 686+20 / LR |
Florida City Gas |
6" PE place out of service |
684+60 to 686+20 |
44-50 LT |
FCG |
| Construction |
684+60 to 686+20 / LR |
Florida City Gas |
6" PE install new, offset under concrete barrier wall |
684+60 to 686+20 |
44-50 LT |
FCG |
| Construction |
|
City of PSL-Engineering |
Remove communication interconnect |
|
|
PSL-E |
| Construction |
557+24 / LR |
Florida City Gas |
2" PE place out of service |
557+24 |
50-65 LT |
FCG |
| Construction |
566+70.38 / RR |
City of PSL |
Adjust existing WM valve box |
566+70.38 |
29 RT |
PSL |
| Construction |
557+24.72 / LR |
FP&L |
Raise overhead distribution line 4' above sign elevation |
557+24.72 |
57.93 LT |
FP&L |
| Construction |
568+83.94 / RR |
City of PSL |
Adjust existing WM valve box |
568+83.94 |
32 RT |
PSL |
| Construction |
576+57.88 / RR |
City of PSL |
Adjust existing WM valve box |
576+57.88 |
33 RT |
PSL |
| Construction |
611+63.31 / LR |
City of PSL |
Adjust existing WM valve box |
611+63.31 |
60 LT |
PSL |
| Construction |
594+72.52 / LR |
City of PSL |
Adjust existing WM valve box |
594+72.52 |
71 LT |
PSL |
| Construction |
602+27.07 / LR |
City of PSL |
Adjust existing WM valve box |
602+27.07 |
69 LT |
PSL |
| Construction |
611+63.31 / LR |
City of PSL |
Adjust existing WM valve box |
611+63.31 |
60 LT |
PSL |
| Construction |
|
City of PSL-Engineering |
Install new wireless communication system |
|
|
PSL-E |
| Drainage |
614+45 to 614+75 / LR |
Florida City Gas |
6" PE install new, offset under S-117 |
614+45 to 614+75 |
44 LT |
FCG |
| Drainage |
614+45 to 614+75 / LR |
Florida City Gas |
6" PE place out of service |
614+45 to 614+75 |
44 LT |
FCG |