EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

District One Construction

Consultant World

Picture of a Florida Roadway

Amendment/Supplemental Amendment Request Process for Consultant Contracts

 

 

When a Consultant identifies a need that will require a Supplemental Amendment Request (SAR) or an Amendment Request (AR), the Consultant Project Principal or Consultant Senior Project Engineer will contact the Construction Project Manager and request approval. Once received, the Consultant will prepare and submit Amendment package and all accompanying documentation to the Construction Project Manager for approval and further processing.

 

 

The Consultant shall submit the Amendment to allow the Department 12 weeks to process, approve, and execute the Amendment.

 

 

 

CCEI = Consultant Construction Engineering and Inspection

 

Return to the District Consultant World Home Page

 

 

Return to the District One Home Page