Date FIN# Contract Subject A/R/P
1/30/12 42563817201 E5M69 SR 400 (I-4) - Repair of Cracked Concrete Slabs A
7/27/10 42334745201 T5318 SR 50 (Colonial Drive) - Replacement of Pavement Due to Ripples A
         
4/16/09 41166525201 E5L60 SR 464 over CSX RR - Unsuitable Material Issue R
4/4/09 41166525201 E5L60 SR464 over CSX - Time Extension for Late Delivery of CSX Signal System A
4/1/09 41166525201 E5L60 SR464 over CSX - Compensation for temporary poles and signal at SW 12th Ave R
         
12/3/08 24160215201 T5164 CR 484 - Deletion of Variability Factor Embankment Quantity A
10/3/07 41715415201 T5152 SR 40 - Remove & Replace Pavement with Surface Deficiencies - Ripples A
3/6/07 23746615201 T5041 SR 520 - Payment of Pile Splices A
         
11/17/06 24249315201 T5043 I-4/John Young Parkway - Delayed Water Use Permit A
9/26/06 24249315201 T5043 I-4/John Young Pkwy - MSE Wall Coating & Elastomeric Box Girder Coating A
         
10/16/06 23929415201 T5044 SR 520 Pipe Installation - Additional Time/Compensation A
1/30/06 24080525201 T5036 SR 44 - Prestress Impact to Supplier A
1/17/06 23831415201 T5063 US441 Pavement Markings & Sand Seal Coating A
9/23/05 40460115201 T5037 SR 528 - Indian River Bridge - Pier 13 Footing Remove/Replace R
8/30/05 23750625201 T5024 SR 520 (Banana River) - Mass Concrete Pour of Footings A
         
8/30/05 23945425604 T5015 SR-436 (SR528 to SR552) Additional Pipe Backfill Material Compensation A
2/9/05 23945425604 T5015 SR436 (JPA w/ City of Orlando) Payment for Meg-a-lugs A
         
6/22/05 23755015201 21485 SR 5 (US 1) - Median Curb, Driveway Delay, Sheet Piling & Bedding Stone Extra Work A
3/8/04 23755015201 21485 SR 5 (US 1) - Bell South Impact (Utility Relocation) A
11/9/03 23755015201 21485 SR 5 (US 1) - Box Culvert Impact A
         
1/31/05 24017415101 21164 SR 426 (Aloma Ave) Non-Payment of Over-thickness FC-3 A
11/8/04 40917315201 T5025 SR15 (US 441) - Base Material Shortage A
         
11/5/04 24075815201 21266 SR 5A (Nova Rd.) Overrun in Mowing A
11/5/04 24075815201 21266 SR 5A (Nova Rd.) Anchor Bolt Tensile Testing A
11/5/04 24075815201 21266 SR 5A (Nova Rd.) Area Wide Cement Shortage A
1/28/03 24075815201 21266 SR 5A (Nova Rd.) Equitable Adjustment - Coquina Rock Boulders in Pipe Trench A
         
10/10/04 24016715201 21447 SR434 Cutting and Patching 85 Open Cut Locations (Install of New Water/Force Mains) A
7/23/04 23929215201 21459 SR 520 - Asphalt Base Removal & Stabilization Issues R
4/12/04 23750615201 21239 SR 520 (Low Level Bridge Replacement) Escalated Workers Compensation Rates A
12/18/03 24075715201 21265 SR 5A (Nova Rd.) Contract Schedule, Computation of Contract Time A
11/13/03 40517615201 21533 SR 15/600 (US 17/92) Assessment of LD's (Soil Conditions, Weather, Shop Drawing Delays) A
9/29/03 23928815201 21588 SR 435 (Kirkman Rd) Maintaining Commercial Material & Payment of Temporary Detection A
1/6/03 24249915201 E5F21 SR 400 (I-4) Add Thru Lanes - Soil Replacement Claim A
1/6/03 24249915201 E5F21 I-4 Auxiliary Lanes Median Edge Drains A
         
5/15/02 23867915201 20605 SR 500 (US 27) Sheet Piling & City of Ocala Electric Pole at Pond E-2 A
4/5/02 23867915201 20605 SR 500 (US 27) Off Duty Law Enforcement A
4/5/02 23867915201 20605 SR 500 (US 27) Borrow Pit Permit & Haul Road Delay Claim A
6/30/00 23867915201 20605 SR 500 (US 27) Restrictions on Burning Operations of Clearing & Grubbing Debris A
         
2/8/02 23967015201 20208 SR 530 (US 192) Claim Issue - Utility Conflict R
9/19/00 23967015201 20208 SR 530 (US 192) Failure to Comply with Specifications ("Pigging" Water Line) A
         
1/10/01 24017815202 20176 SR414 (Maitland Blvd) Unforeseen Conditions (Hardpan) & Broken Sewer Line A
11/13/00 23863515201 20443 SR 200 - Utility Conflicts, Differing Site Condition (Pond 3), Conflict w/ Electrical Guy Wires & Poles, Timely Installation of Stored Materials (4 Issues) A
3/30/00 24012115201 19997 SR 15 (US 17-92) Adjusting Contract Incentive Time A