FLORIDA DEPARTMENT OF TRANSPORTATION --- STATE MATERIALS OFFICE      
RIDE ACCEPTANCE
PROJECT NUMBER 97930-3363  FINANCIAL PROJECT NO. 2325941 52 01
FLORIDA TURNPIKE   SR 91 TURNPIKE  TURNPIKE DISTRICT
ENGLISH JOB
       
       
       
         
LANES NUMBER OF RATED LOTS NUMBER OF RATED LOTS RN>=4.21 NUMBER OF RATED LOTS
4.10>RN >3.69
NUMBER OF RATED LOTS RN<=3.69
NORTHBOUND TRAFFIC LANE 60 55 2 0
       
NORTHBOUND PASSING LANE 60 54 2 0
       
SOUTHBOUND TRAFFIC LANE 60 53 3 0
       
SOUTHBOUND PASSING LANE 60 17 6 0
       
TOTAL 240 179 13 0
       
SMOOTHNESS PAYMENT PER LOT ( A ) =     $500.00
% OF LOTS WITH RN < 4.10 ( Pb) =     5.42%
% OF LOTS WITH RN >= 4.21 ( Pa) =     74.58%
PERCENT OF BONUS LOTS (P) = Pa - 2Pb ( P ) = 74.58% - ( 2 * 05.42%) 63.75%
SMOOTHNESS FACTOR (B) = (P-70.0)/25.0 ( B ) = ( 63.75 - 70 ) / 25 0.00
TOTAL NUMBER OF RATED LOTS ( C ) =   240
TOTAL SMOOTHNESS PAYMENT ( A * B * C ) = $500.00 * 0.00 * 240 $0.00
       
         
NOTE 1:  THESE EXAMPLE CALCULATIONS ARE BASED ON FDOT SPECIFICATION 330-12.7.1, AS OF 6/20/03
NOTE 2:  SMOOTHNESS FACTOR CANNOT BE LESS THAN 0 OR GREATER THAN 1.00.
NOTE 3:  TOTAL SMOOTHNESS PAYMENT CANNOT EXCEED 3% OF CONTRACT PRICE.
       
MILEPOST  BMP.  25.576 TO   EMP.  32.739
RIDE ACCEPTANCE -- 6" SAMPLING INTERVALS
DATE TESTED 12/8/98  UNIT 1 DOT 24741
FRICTION COURSE FC-5