EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Construction

Office of Construction / Asphalt

Ride Acceptance Results

Picture of a Florida Roadway
FLORIDA DEPARTMENT OF TRANSPORTATION --- STATE MATERIALS OFFICE      
RIDE EVALUATION
PROJECT NUMBER 97110-3313  FINANCIAL PROJECT NO. 2428591 52 01
FLORIDA TURNPIKE   SR 91 TURNPIKE  TURNPIKE DISTRICT
METRIC JOB
       
       
       
         
LANES NUMBER OF RATED LOTS NUMBER OF RATED LOTS RN>=4.21 NUMBER OF RATED LOTS
4.10>RN >3.69
NUMBER OF RATED LOTS RN<=3.69
       
SOUTHBOUND TRAFFIC LANE 241 125 22 8
       
SOUTHBOUND PASSING LANE 238 51 95 19
       
TOTAL 479 176 117 27
       
SMOOTHNESS PAYMENT PER LOT ( A ) =     $310.00
% OF LOTS WITH RN < 4.10 ( Pb) =     30.06%
% OF LOTS WITH RN >= 4.21 ( Pa) =     36.74%
PERCENT OF BONUS LOTS (P) = Pa - 2Pb ( P ) = 36.74% - ( 2 * 30.06%) -23.38%
SMOOTHNESS FACTOR (B) = (P-70.0)/25.0 ( B ) = ( -23.38 - 70 ) / 25 0.00
TOTAL NUMBER OF RATED LOTS ( C ) =   479
TOTAL SMOOTHNESS PAYMENT ( A * B * C ) = $310.00 * 0.00 * 479 $0.00
       
         
NOTE 1:  THESE EXAMPLE CALCULATIONS ARE BASED ON FDOT SPECIFICATION 330-12.7.1, AS OF 6/20/03
NOTE 2:  SMOOTHNESS FACTOR CANNOT BE LESS THAN 0 OR GREATER THAN 1.00.
NOTE 3:  TOTAL SMOOTHNESS PAYMENT CANNOT EXCEED 3% OF CONTRACT PRICE.
       
KILOMETERPOST  BKP.  453.561 TO   EKP.  479.221
RIDE EVALUATION -- 6" SAMPLING INTERVALS
DATE TESTED 12/13/99  UNIT 5 DOT 24388
FRICTION COURSE FC-5