| FLORIDA DEPARTMENT OF TRANSPORTATION --- STATE MATERIALS OFFICE | ||||
| RIDE ACCEPTANCE | ||||
| PROJECT NUMBER 35090-3436 FINANCIAL PROJECT NO. 2134391 52 01 | ||||
| MADISON COUNTY SR 8 / I-10 DISTRICT 2 | ||||
| ENGLISH JOB | ||||
| LANES | NUMBER OF RATED LOTS | NUMBER OF RATED LOTS RN>=4.21 |
NUMBER OF RATED LOTS 4.10>RN>3.69 |
NUMBER OF RATED LOTS RN<=3.69 |
| EASTBOUND TRAFFIC LANE | 51 | 25 | 2 | 0 |
| EASTBOUND PASSING LANE | 51 | 44 | 2 | 0 |
| WESTBOUND TRAFFIC LANE | 52 | 50 | 0 | 0 |
| WESTBOUND PASSING LANE | 52 | 48 | 0 | 0 |
| TOTAL | 206 | 167 | 4 | 0 |
| SMOOTHNESS PAYMENT PER LOT | ( A ) = | $500.00 | ||
| % OF LOTS WITH RN < 4.10 | ( Pb) = | 1.94% | ||
| % OF LOTS WITH RN >= 4.21 | ( Pa) = | 81.07% | ||
| PERCENT OF BONUS LOTS (P) = Pa - 2Pb | ( P ) = | 81.07% - ( 2 * 01.94% ) | 77.18% | |
| SMOOTHNESS FACTOR (B) = (P-70.0)/25.0 | ( B ) = | ( 77.18 - 70 ) / 25 | 0.29 | |
| TOTAL NUMBER OF RATED LOTS | ( C ) = | 206 | ||
| TOTAL SMOOTHNESS PAYMENT | ( A * B * C ) = | $500.00 * 0.29 * 206 | $29,870.00 | |
| NOTE 1: THESE EXAMPLE CALCULATIONS ARE BASED ON FDOT SPECIFICATION 330-12.7.1, AS OF 6/20/03 | ||||
| NOTE 2: SMOOTHNESS FACTOR CANNOT BE LESS THAN 0 OR GREATER THAN 1.00. | ||||
| NOTE 3: TOTAL SMOOTHNESS PAYMENT CANNOT EXCEED 3% OF CONTRACT PRICE. | ||||
| MILEPOST BMP. 0 TO EMP. 5.447 | ||||
| RIDE ACCEPTANCE -- 6" SAMPLING INTERVALS | ||||
| DATE TESTED 7/23/98 UNIT 2 DOT 24740 | ||||
| FRICTION COURSE FC-5 | ||||