| FLORIDA DEPARTMENT OF TRANSPORTATION --- STATE MATERIALS OFFICE | ||||
| RIDE ACCEPTANCE | ||||
| PROJECT NUMBER 34010-0000 FINANCIAL PROJECT NO. 2104311 52 01 | ||||
| LEVY COUNTY SR 55 / US 19 DISTRICT 2 | ||||
| METRIC JOB | ||||
| LANES | NUMBER OF RATED LOTS | NUMBER OF RATED LOTS RN>=4.21 |
NUMBER OF RATED LOTS 4.10>RN>3.69 |
NUMBER OF RATED LOTS RN<=3.69 |
| EASTBOUND TRAFFIC LANE | 99 | 98 | 0 | 0 |
| EASTBOUND PASSING LANE | 99 | 98 | 0 | 0 |
| WESTBOUND TRAFFIC LANE | 98 | 95 | 0 | 0 |
| WESTBOUND PASSING LANE | 98 | 78 | 4 | 0 |
| TOTAL | 394 | 369 | 4 | 0 |
| SMOOTHNESS PAYMENT PER LOT | ( A ) = | $310.00 | ||
| % OF LOTS WITH RN < 4.10 | ( Pb) = | 1.02% | ||
| % OF LOTS WITH RN >= 4.21 | ( Pa) = | 93.65% | ||
| PERCENT OF BONUS LOTS (P) = Pa - 2Pb | ( P ) = | 93.65% - ( 2 * 01.02% ) | 91.62% | |
| SMOOTHNESS FACTOR (B) = (P-70.0)/25.0 | ( B ) = | ( 91.62 - 70 ) / 25 | 0.86 | |
| TOTAL NUMBER OF RATED LOTS | ( C ) = | 394 | ||
| TOTAL SMOOTHNESS PAYMENT | ( A * B * C ) = | $310.00 * 0.86 * 394 | $105,040.40 | |
| NOTE 1: THESE EXAMPLE CALCULATIONS ARE BASED ON FDOT SPECIFICATION 330-12.7.1, AS OF 6/20/03 | ||||
| NOTE 2: SMOOTHNESS FACTOR CANNOT BE LESS THAN 0 OR GREATER THAN 1.00. | ||||
| NOTE 3: TOTAL SMOOTHNESS PAYMENT CANNOT EXCEED 3% OF CONTRACT PRICE. | ||||
| KILOMETERPOST BKP. 0.574 TO EKP. 10.534 | ||||
| RIDE ACCEPTANCE -- 6" SAMPLING INTERVALS | ||||
| DATE TESTED 7/26/01 UNIT 3 DOT 24725 | ||||
| FRICTION COURSE FC-5 | ||||