| NORTHBOUND TRAFFIC LANE | 37 | 32 | 0 | 0 |
| NORTHBOUND MIDDLE LANE | 47 | 39 | 1 | 0 |
| NORTHBOUND PASSING LANE | 47 | 42 | 0 | 0 |
| SOUTHBOUND TRAFFIC LANE | 37 | 36 | 0 | 0 |
| SOUTHBOUND MIDDLE' LANE | 48 | 41 | 0 | 0 |
| SOUTHBOUND PASSING LANE | 49 | 38 | 1 | 0 |
| TOTAL | 265 | 228 | 2 | 0 |
| SMOOTHNESS PAYMENT PER LOT | ( A ) = | $310.00 | ||
| % OF LOTS WITH RN < 4.10 | ( Pb) = | 0.75% | ||
| % OF LOTS WITH RN >= 4.21 | ( Pa) = | 86.04% | ||
| PERCENT OF BONUS LOTS (P) = Pa - 2Pb | ( P ) = | 86.04% - ( 2 * 00.75% ) | 84.53% | |
| SMOOTHNESS FACTOR (B) = (P-70.0)/25.0 | ( B ) = | ( 84.53 - 70 ) / 25 | 0.58 | |
| TOTAL NUMBER OF RATED LOTS | ( C ) = | 265 | ||
| TOTAL SMOOTHNESS PAYMENT | ( A * B * C ) = | $310.00 * 0.58 * 265 | $47,647.00 | |
| NOTE 1: THESE EXAMPLE CALCULATIONS ARE BASED ON FDOT SPECIFICATION 330-12.7.1, AS OF 6/20/03 | ||||
| NOTE 2: SMOOTHNESS FACTOR CANNOT BE LESS THAN 0 OR GREATER THAN 1.00. | ||||
| NOTE 3: TOTAL SMOOTHNESS PAYMENT CANNOT EXCEED 3% OF CONTRACT PRICE. | ||||
| KILOMETERPOST BKP. 5.312 TO EKP. 12.683 | ||||
| RIDE ACCEPTANCE -- 6" SAMPLING INTERVALS | ||||
| DATE TESTED 9/28/00 UNIT 5 DOT 24388 | ||||
| FRICTION COURSE FC-5 | ||||