Putnam County Construction

Max Brewer Bridge

 

Putnam Project Information (33kb)

Adopted Five Year Citizen's Plan Report (61kb)

State Road 100

 

Build 12-foot wide asphalt bike trail from Holloway Road to Roberts Lane (4.5 miles).

 

Project start date: August 31, 2012

 

Estimated completion: 320 days (Summer of 2013)

 

Contractor is Callaway Contracting Inc.

State Road 100

 

Repairs to the bike trail from Goodson Prairie Road to Palmetto Branch Trail (6 miles)

 

Project start date: February 7, 2013

 

Estimated completion: 200 days (Fall 2013)

 

Contractor is Westwind Contracting Inc.