State Road 100
Build 12-foot wide asphalt bike trail from Holloway Road to Roberts Lane (4.5 miles).
Project start date: August 31, 2012
Estimated completion: 320 days (Summer of 2013)
Contractor is Callaway Contracting Inc.
State Road 100
Repairs to the bike trail from Goodson Prairie Road to Palmetto Branch Trail (6 miles)
Project start date: February 7, 2013
Estimated completion: 200 days (Fall 2013)
Contractor is Westwind Contracting Inc.