State Road A1A
Repainting the Amelia River bridges.
Project start date: March 23, 2012
Estimated completion: 365 days (Spring 2013)
Contractor is Gemstone, LLC of Key West
US 301
Adding lanes from the Duval County line to the four-lane just south of Callahan (14 miles).
Project start date: November 14, 2011
Estimated completion: 1,200 days (Fall of 2014)
Contractor is Anderson Columbia Company of Lake City
State Road A1A
Building bike trail from the Nassau Sound Bridge to Peters Point Park (6 miles).
Project start date: October 15, 2012
Estimated completion: 120 days (Early 2013)
Contractor is J.B. Coxwell Contracting Inc.