Madison County Construction

Max Brewer Bridge

 

Madison Project Information (8kb)

Adopted Five Year Citizen's Plan Report

Interstate 10

 

Resurface from the Suwannee County line (Suwannee River Bridge) to east of State Road 53 (9.2 miles)

 

Project start date: October 8, 2012

 

Estimated completion: 200 days (Spring of 2013)

 

Contractor: Anderson Columbia Company Inc.